1.5. STORK Sustainability

Estimate at Completion (Data updated on: 04/07/2017)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
10/2014 954324.72 849349.00
09/2014 943721.11 849349.00
08/2014 943721.11 849349.00
07/2014 943721.11 849349.00
06/2014 954324.72 849349.00
05/2014 943721.11 849349.00
04/2014 933350.55 849349.00
03/2014 894051.58 849349.00
02/2014 857928.28 849349.00
01/2014 849349.00 849349.00
12/2013 824610.68 849349.00
11/2013 1147768.92 849349.00
10/2013 1088908.97 849349.00
09/2013 1061686.25 849349.00
08/2013 1011129.76 849349.00
07/2013 999234.12 849349.00
06/2013 999234.12 849349.00
05/2013 903562.77 849349.00
04/2013 923205.43 849349.00
03/2013 903562.77 849349.00