1.5. STORK Sustainability

Estimate at Completion (Data updated on: 04/07/2017)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
06/2016 849349.00 849349.00
05/2016 849349.00 849349.00
04/2016 857928.28 849349.00
03/2016 857928.28 849349.00
02/2016 857928.28 849349.00
01/2016 857928.28 849349.00
12/2015 857928.28 849349.00
11/2015 923205.43 849349.00
10/2015 866682.65 849349.00
09/2015 933350.55 849349.00
08/2015 857928.28 849349.00
07/2015 840939.60 849349.00
06/2015 832695.10 849349.00
05/2015 824610.68 849349.00
04/2015 875617.53 849349.00
03/2015 875617.53 849349.00
02/2015 866682.65 849349.00
01/2015 857928.28 849349.00
12/2014 875617.53 849349.00
11/2014 857928.28 849349.00