The cluster deals with information that is exchanged cross-border, typically taking place in sector specific projects. The cluster addresses topics such as semantics, information availability and usage, trust and privacy and the catalogue of services.
More details about this action are available on a dedicated page of the official ISA website.
The overall efficiency rating is the average of the "Schedule Perfomance Index" (SPI) rating and the "Percentage of delay" (% of delay) rating
The SPI rating is based on the action's SPI : 1.00
The % of delay rating is based on the action's % delay: 0.00
Direct involvement of MARE and JRC stakeholders throughout the study.
Participation in missions
Participation in progress meetings
Participation in workshops
70% of required attendees should be present in each of these.
Rate at which deliverable recipients comment on the deliverable.
65% of those addressed to comment should do so.
Target of 10 meetings throughout the duration of the study.
Representation rate of the seven user communities.
Extent to which the four IOP layers of the EIF are covered in the analysis (legal, organizational, semantic and technical opportunities and barriers for realizing the information services).