Budget at completion: 571869,00
Start Date: 01/11/2011
End Date: 02/06/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/02/2013 571869.00 184560.80 185894.00 185894.00 -0.01 0.32
01/01/2013 571869.00 163362.92 163396.25 163396.25 0.00 0.29
01/12/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/11/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/10/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/09/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/08/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/07/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/06/2012 571869.00 149640.00 149640.00 149640.00 0.00 0.26
01/05/2012 571869.00 142158.00 149640.00 149640.00 -0.05 0.25
01/04/2012 571869.00 130935.00 124247.37 124247.37 0.05 0.23
01/03/2012 571869.00 130935.00 96181.81 96181.81 0.36 0.23
01/02/2012 571869.00 127194.00 66779.81 66779.81 0.90 0.22
01/01/2012 571869.00 66589.80 38714.26 38714.26 0.72 0.12
01/12/2011 571869.00 32920.80 19228.17 19228.17 0.71 0.06
01/11/2011 571869.00 8978.40 5523.62 5523.62 0.63 0.02