Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 571869,00
Start Date: 01/11/2011
End Date: 02/06/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/06/2016 571869.00 571869.00 571869.00 571869.00 0.00 1.00
01/05/2016 571869.00 567109.50 571487.32 571487.32 -0.01 0.99
01/04/2016 571869.00 558102.00 565739.00 565739.00 -0.01 0.98
01/03/2016 571869.00 551807.00 556131.50 556131.50 -0.01 0.96
01/02/2016 571869.00 544287.60 548399.00 548399.00 -0.01 0.95
01/01/2016 571869.00 541104.20 542701.50 542701.50 0.00 0.95
01/12/2015 571869.00 531628.80 535756.01 535756.01 -0.01 0.93
01/11/2015 571869.00 525793.40 529325.34 529325.34 -0.01 0.92
01/10/2015 571869.00 522194.00 521373.89 521373.89 0.00 0.91
01/09/2015 571869.00 522194.00 520963.83 520963.83 0.00 0.91
01/08/2015 571869.00 522194.00 520553.77 520553.77 0.00 0.91
01/07/2015 571869.00 517067.30 520162.35 520162.35 -0.01 0.90
01/06/2015 571869.00 514780.30 518710.83 518710.83 -0.01 0.90
01/05/2015 571869.00 512866.30 517322.42 517322.42 -0.01 0.90
01/04/2015 571869.00 503557.50 515997.11 515997.11 -0.02 0.88
01/03/2015 571869.00 503557.50 514608.68 514608.68 -0.02 0.88
01/02/2015 571869.00 502206.20 513220.28 513220.28 -0.02 0.88
01/01/2015 571869.00 488965.80 511958.08 511958.08 -0.04 0.86
01/12/2014 571869.00 449279.30 492314.37 492314.37 -0.09 0.79
01/11/2014 571869.00 437578.74 472962.26 472962.26 -0.07 0.77