1.8. Trusted Exchange Platform (E-TRUSTEX)

Earned Value Analysis for the "Action" Level (Data updated on: 28/07/2017)

Budget at completion: 7200000,00
Start Date: 01/04/2010
End Date: 31/03/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/10/2010 7200000.00 279000.00 279754.60 279754.60 0.00 0.04
01/09/2010 7200000.00 240000.00 241104.29 241104.29 0.00 0.03
01/08/2010 7200000.00 201000.00 200613.50 200613.50 0.00 0.03
01/07/2010 7200000.00 159000.00 160122.70 160122.70 -0.01 0.02
01/06/2010 7200000.00 120000.00 119631.90 119631.90 0.00 0.02
01/05/2010 7200000.00 78000.00 79141.10 79141.10 -0.01 0.01
01/04/2010 7200000.00 39000.00 40490.80 40490.80 -0.04 0.01
01/03/2010 7200000.00 0.00 0.00 0.00 0.00 0.00