Earned Value Analysis for the "Action" Level (Data updated on: 28/07/2017)
Budget at completion: 7200000,00
Start Date: 01/04/2010
End Date: 31/03/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/06/2017 |
7200000.00 |
7200000.00 |
7200000.00 |
7200000.00 |
0.00 |
0.00 |
|
01/05/2017 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/04/2017 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/03/2017 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/02/2017 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/01/2017 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/12/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/11/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/10/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/09/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/08/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/07/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/06/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/05/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/04/2016 |
7200000.00 |
6940000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/03/2016 |
7200000.00 |
6935000.00 |
7200000.00 |
7200000.00 |
-0.04 |
0.00 |
|
01/02/2016 |
7200000.00 |
6930000.00 |
7113703.90 |
7113703.90 |
-0.03 |
0.00 |
|
01/01/2016 |
7200000.00 |
6895000.00 |
7034911.79 |
7034911.79 |
-0.02 |
0.00 |
|
01/12/2015 |
7200000.00 |
6777750.00 |
7200000.00 |
7200000.00 |
-0.06 |
0.00 |
|
01/11/2015 |
7200000.00 |
6672750.00 |
6821814.52 |
6821814.52 |
-0.02 |
0.00 |