Earned Value Analysis for the "Action" Level (Data updated on: 23/03/2016)
Budget at completion: 10750000,00
Start Date: 01/07/2010
End Date: 31/03/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/11/2012 |
10750000.00 |
5442500.00 |
5305769.23 |
5305769.23 |
0.03 |
0.51 |
|
01/10/2012 |
10750000.00 |
5289500.00 |
5229615.39 |
5229615.39 |
0.01 |
0.49 |
|
01/09/2012 |
10750000.00 |
5141000.00 |
5150000.00 |
5150000.00 |
0.00 |
0.48 |
|
01/08/2012 |
10750000.00 |
5105000.00 |
5080769.23 |
5080769.23 |
0.00 |
0.47 |
|
01/07/2012 |
10750000.00 |
4997000.00 |
5001153.85 |
5001153.85 |
0.00 |
0.46 |
|
01/06/2012 |
10750000.00 |
4893500.00 |
4925000.00 |
4925000.00 |
-0.01 |
0.46 |
|
01/05/2012 |
10750000.00 |
4825500.00 |
4626153.85 |
4626153.85 |
0.04 |
0.45 |
|
01/04/2012 |
10750000.00 |
4694500.00 |
4298846.15 |
4298846.15 |
0.09 |
0.44 |
|
01/03/2012 |
10750000.00 |
3890000.00 |
4000000.00 |
4000000.00 |
-0.03 |
0.36 |
|
01/02/2012 |
10750000.00 |
3855500.00 |
4000000.00 |
4000000.00 |
-0.04 |
0.36 |
|
01/01/2012 |
10750000.00 |
3850500.00 |
4000000.00 |
4000000.00 |
-0.04 |
0.36 |
|
01/12/2011 |
10750000.00 |
3810500.00 |
4000000.00 |
4000000.00 |
-0.05 |
0.35 |
|
01/11/2011 |
10750000.00 |
3550500.00 |
3837913.87 |
3837913.87 |
-0.07 |
0.33 |
|
01/10/2011 |
10750000.00 |
3355500.00 |
3675827.79 |
3675827.79 |
-0.09 |
0.31 |
|
01/09/2011 |
10750000.00 |
3234000.00 |
3520599.01 |
3520599.01 |
-0.08 |
0.30 |
|
01/08/2011 |
10750000.00 |
3098000.00 |
3358570.44 |
3358570.44 |
-0.08 |
0.29 |
|
01/07/2011 |
10750000.00 |
2953500.00 |
3189176.97 |
3189176.97 |
-0.07 |
0.27 |
|
01/06/2011 |
10750000.00 |
2824000.00 |
3034513.34 |
3034513.34 |
-0.07 |
0.26 |
|
01/05/2011 |
10750000.00 |
2644500.00 |
2830881.74 |
2830881.74 |
-0.07 |
0.25 |
|
01/04/2011 |
10750000.00 |
2456500.00 |
2627250.13 |
2627250.13 |
-0.06 |
0.23 |