Earned Value Analysis for the "Action" Level (Data updated on: 23/03/2016)
Budget at completion: 10750000,00
Start Date: 01/07/2010
End Date: 31/03/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/03/2016 |
10750000.00 |
10750000.00 |
10750000.00 |
10750000.00 |
0.00 |
1.00 |
|
01/02/2016 |
10750000.00 |
10639000.00 |
10618320.61 |
10618320.61 |
0.00 |
0.99 |
|
01/01/2016 |
10750000.00 |
10627000.00 |
10498091.60 |
10498091.60 |
0.01 |
0.99 |
|
01/12/2015 |
10750000.00 |
10411000.00 |
10377862.60 |
10377862.60 |
0.00 |
0.97 |
|
01/11/2015 |
10750000.00 |
10007500.00 |
10183778.68 |
10183778.68 |
-0.02 |
0.93 |
|
01/10/2015 |
10750000.00 |
9994000.00 |
10006571.61 |
10006571.61 |
0.00 |
0.93 |
|
01/09/2015 |
10750000.00 |
9602000.00 |
9820926.11 |
9820926.11 |
-0.02 |
0.89 |
|
01/08/2015 |
10750000.00 |
9190000.00 |
9635280.61 |
9635280.61 |
-0.05 |
0.85 |
|
01/07/2015 |
10750000.00 |
9125500.00 |
9458073.55 |
9458073.55 |
-0.04 |
0.85 |
|
01/06/2015 |
10750000.00 |
8911000.00 |
9263989.62 |
9263989.62 |
-0.04 |
0.83 |
|
01/05/2015 |
10750000.00 |
8899000.00 |
9078344.13 |
9078344.13 |
-0.02 |
0.83 |
|
01/04/2015 |
10750000.00 |
8887000.00 |
8901137.06 |
8901137.06 |
0.00 |
0.83 |
|
01/03/2015 |
10750000.00 |
8552500.00 |
8949311.93 |
8949311.93 |
-0.04 |
0.96 |
|
01/02/2015 |
10750000.00 |
8530000.00 |
8639974.59 |
8639974.59 |
-0.01 |
0.79 |
|
01/01/2015 |
10750000.00 |
8515000.00 |
8571948.30 |
8571948.30 |
-0.01 |
0.79 |
|
01/12/2014 |
10750000.00 |
8400000.00 |
8497119.39 |
8497119.39 |
-0.01 |
0.78 |
|
01/11/2014 |
10750000.00 |
8287500.00 |
8389627.07 |
8389627.07 |
-0.01 |
0.77 |
|
01/10/2014 |
10750000.00 |
8272500.00 |
8296155.49 |
8296155.49 |
0.00 |
0.77 |
|
01/09/2014 |
10750000.00 |
7652500.00 |
8188663.19 |
8188663.19 |
-0.07 |
0.71 |
|
01/08/2014 |
10750000.00 |
7637500.00 |
8126211.43 |
8126211.43 |
-0.06 |
0.71 |