Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)
Budget at completion: 1347976,00
Start Date: 01/09/2010
End Date: 04/11/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/11/2016 |
1347976.00 |
1347976.00 |
1347976.00 |
1347976.00 |
0.00 |
1.00 |
|
01/10/2016 |
1347976.00 |
1293857.50 |
1347743.64 |
1347743.64 |
-0.04 |
0.96 |
|
01/09/2016 |
1347976.00 |
1273706.20 |
1344221.40 |
1344221.40 |
-0.05 |
0.94 |
|
01/08/2016 |
1347976.00 |
1273706.20 |
1320295.88 |
1320295.88 |
-0.04 |
0.94 |
|
01/07/2016 |
1347976.00 |
1250156.50 |
1275027.61 |
1275027.61 |
-0.02 |
0.93 |
|
01/06/2016 |
1347976.00 |
1230440.75 |
1249709.92 |
1249709.92 |
-0.02 |
0.91 |
|
01/05/2016 |
1347976.00 |
1214976.50 |
1246256.04 |
1246256.04 |
-0.03 |
0.90 |
|
01/04/2016 |
1347976.00 |
1199576.25 |
1223392.44 |
1223392.44 |
-0.02 |
0.89 |
|
01/03/2016 |
1347976.00 |
1193615.75 |
1214554.89 |
1214554.89 |
-0.02 |
0.89 |
|
01/02/2016 |
1347976.00 |
1190098.25 |
1195438.45 |
1195438.45 |
0.00 |
0.88 |
|
01/01/2016 |
1347976.00 |
1172661.25 |
1176262.32 |
1176262.32 |
0.00 |
0.87 |
|
01/12/2015 |
1347976.00 |
1155978.00 |
1155978.00 |
1155978.00 |
0.00 |
1.00 |
|
01/11/2015 |
1347976.00 |
1071480.75 |
1155978.00 |
1155978.00 |
-0.07 |
0.93 |
|
01/10/2015 |
1347976.00 |
1039520.00 |
1103618.42 |
1103618.42 |
-0.06 |
0.90 |
|
01/09/2015 |
1347976.00 |
1039520.00 |
1069851.67 |
1069851.67 |
-0.03 |
0.90 |
|
01/08/2015 |
1347976.00 |
1029427.70 |
1030750.45 |
1030750.45 |
0.00 |
0.89 |
|
01/07/2015 |
1347976.00 |
1008516.15 |
992835.08 |
992835.08 |
0.02 |
0.87 |
|
01/06/2015 |
1347976.00 |
960103.25 |
966828.77 |
966828.77 |
-0.01 |
0.83 |
|
01/05/2015 |
1347976.00 |
934842.25 |
944087.54 |
944087.54 |
-0.01 |
0.81 |
|
01/04/2015 |
1347976.00 |
909368.00 |
969657.06 |
969657.06 |
-0.06 |
0.67 |