4.2.6. Interoperable test bed

Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 331015,00
Start Date: 02/12/2013
End Date: 31/08/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/08/2016 331015.00 331015.00 331003.96 331003.96 0.00 1.00
01/07/2016 331015.00 318699.90 330761.06 330761.06 -0.04 0.96
01/06/2016 331015.00 305908.60 329409.50 329409.50 -0.07 0.92
01/05/2016 331015.00 285966.40 305020.88 305020.88 -0.06 0.86
01/04/2016 331015.00 267668.30 291140.98 291140.98 -0.08 0.81
01/03/2016 331015.00 241892.30 275116.89 275116.89 -0.12 0.73
01/02/2016 331015.00 211886.10 252498.76 252498.76 -0.16 0.64
01/01/2016 331015.00 189512.40 231637.06 231637.06 -0.18 0.57
01/12/2015 331015.00 176041.50 210775.41 210775.41 -0.16 0.53
01/11/2015 331015.00 169545.00 187926.91 187926.91 -0.10 0.51
01/10/2015 331015.00 160425.00 163862.74 163862.74 -0.02 0.48
01/09/2015 331015.00 160425.00 160425.00 160425.00 0.00 0.48
01/08/2015 331015.00 160425.00 160425.00 160425.00 0.00 0.48
01/07/2015 331015.00 160425.00 160425.00 160425.00 0.00 0.48
01/06/2015 331015.00 157734.40 159199.69 159199.69 -0.01 0.48
01/05/2015 331015.00 145000.40 152875.11 152875.11 -0.05 0.44
01/04/2015 331015.00 122914.00 141295.55 141295.55 -0.13 0.37
01/03/2015 331015.00 94458.80 109613.40 109613.40 -0.14 0.29
01/02/2015 331015.00 71182.50 76615.66 76615.66 -0.07 0.22
01/01/2015 331015.00 62985.90 62707.78 62707.78 0.00 0.19