Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)
Budget at completion: 636135,00
Start Date: 06/01/2014
End Date: 12/06/2105
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/12/2016 |
636135.00 |
636135.00 |
628729.06 |
628729.06 |
0.01 |
1.00 |
|
01/11/2016 |
636135.00 |
625677.36 |
628508.47 |
628508.47 |
0.00 |
0.98 |
|
01/10/2016 |
636135.00 |
625677.36 |
625183.86 |
625183.86 |
0.00 |
0.98 |
|
01/09/2016 |
636135.00 |
618672.45 |
613487.19 |
613487.19 |
0.01 |
0.97 |
|
01/08/2016 |
636135.00 |
554835.72 |
564200.27 |
564200.27 |
-0.02 |
0.87 |
|
01/07/2016 |
636135.00 |
519345.68 |
525520.07 |
525520.07 |
-0.01 |
0.82 |
|
01/06/2016 |
636135.00 |
514131.87 |
501219.70 |
501219.70 |
0.03 |
0.79 |
|
01/05/2016 |
636135.00 |
476891.62 |
470838.01 |
470838.01 |
0.01 |
0.73 |
|
01/04/2016 |
636135.00 |
468788.98 |
462431.94 |
462431.94 |
0.01 |
0.72 |
|
01/03/2016 |
636135.00 |
458463.29 |
446387.35 |
446387.35 |
0.03 |
0.70 |
|
01/02/2016 |
636135.00 |
441430.66 |
417510.33 |
417510.33 |
0.06 |
0.68 |
|
01/01/2016 |
636135.00 |
372270.00 |
377932.84 |
377932.84 |
-0.01 |
0.57 |
|
01/12/2015 |
636135.00 |
315708.74 |
343237.77 |
343237.77 |
-0.08 |
0.48 |
|
01/11/2015 |
636135.00 |
297752.81 |
300224.58 |
300224.58 |
-0.01 |
0.46 |
|
01/10/2015 |
636135.00 |
261011.70 |
251958.55 |
251958.55 |
0.04 |
0.40 |
|
01/09/2015 |
636135.00 |
257452.40 |
276540.84 |
276540.84 |
-0.07 |
0.39 |
|
01/08/2015 |
636135.00 |
249630.23 |
257675.72 |
257675.72 |
-0.03 |
0.38 |
|
01/07/2015 |
636135.00 |
231352.36 |
235476.25 |
235476.25 |
-0.02 |
0.35 |
|
01/06/2015 |
636135.00 |
218225.20 |
210375.57 |
210375.57 |
0.04 |
0.33 |
|
01/05/2015 |
636135.00 |
195702.85 |
195652.84 |
195652.84 |
0.00 |
0.30 |