2.4. Data Communication Network Service (sTESTA)

Estimate at Completion (Data updated on: 19/04/2017)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
03/2017 9700002.00 9700002.00
02/2017 9797981.82 9700002.00
01/2017 9797981.82 9700002.00
12/2016 9797981.82 9700002.00
11/2016 9797981.82 9700002.00
10/2016 9897961.22 9700002.00
09/2016 9897961.22 9700002.00
08/2016 9897961.22 9700002.00
07/2016 10000002.06 9700002.00
06/2016 10000002.06 9700002.00
05/2016 10000002.06 9700002.00
04/2016 10000002.06 9700002.00
03/2016 10000002.06 9700002.00
02/2016 10000002.06 9700002.00
01/2016 10104168.75 9700002.00
12/2015 10104168.75 9700002.00
11/2015 10210528.42 9700002.00
10/2015 10543480.43 9700002.00
09/2015 10543480.43 9700002.00
08/2015 11411767.06 9700002.00