Estimate at Completion (Data updated on: 12/07/2016)
|
Measured period |
Estimate at Completion (Euro) |
Budget at Completion (Euro) |
|
06/2016 |
329266.00 |
329266.00 |
|
05/2016 |
329266.00 |
329266.00 |
|
04/2016 |
354049.46 |
329266.00 |
|
03/2016 |
339449.48 |
329266.00 |
|
02/2016 |
319675.73 |
329266.00 |
|
01/2016 |
316601.92 |
329266.00 |
|
12/2015 |
329266.00 |
329266.00 |
|
11/2015 |
326005.94 |
329266.00 |
|
10/2015 |
339449.48 |
329266.00 |
|
09/2015 |
329266.00 |
329266.00 |
|
08/2015 |
329266.00 |
329266.00 |
|
07/2015 |
329266.00 |
329266.00 |
|
06/2015 |
329266.00 |
329266.00 |
|
05/2015 |
310628.30 |
329266.00 |
|
04/2015 |
296636.04 |
329266.00 |
|
03/2015 |
299332.73 |
329266.00 |
|
02/2015 |
293987.50 |
329266.00 |
|
01/2015 |
307725.23 |
329266.00 |
|
09/2014 |
329266.00 |
329266.00 |
|
08/2014 |
339449.48 |
329266.00 |