Earned Value Analysis for the "Action" Level (Data updated on: 12/02/2018)
Budget at completion: 2047885,00
Start Date: 12/07/2012
End Date: 31/12/2017
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/12/2017 |
2047885.00 |
2047885.00 |
2047885.00 |
2047885.00 |
0.00 |
1.00 |
|
01/09/2017 |
2047885.00 |
2003291.00 |
2039885.00 |
2039885.00 |
-0.02 |
0.98 |
|
01/08/2017 |
2047885.00 |
2003291.00 |
2037300.38 |
2037300.38 |
-0.02 |
0.98 |
|
01/07/2017 |
2047885.00 |
2003291.00 |
2030085.38 |
2030085.38 |
-0.01 |
0.98 |
|
01/06/2017 |
2047885.00 |
2003291.00 |
2022316.16 |
2022316.16 |
-0.01 |
0.98 |
|
01/05/2017 |
2047885.00 |
1991429.00 |
2016884.69 |
2016884.69 |
-0.01 |
0.97 |
|
01/04/2017 |
2047885.00 |
1991429.00 |
2011206.34 |
2011206.34 |
-0.01 |
0.97 |
|
01/03/2017 |
2047885.00 |
1991429.00 |
2005846.32 |
2005846.32 |
-0.01 |
0.97 |
|
01/02/2017 |
2047885.00 |
1985105.00 |
1987319.38 |
1987319.38 |
0.00 |
0.97 |
|
01/01/2017 |
2047885.00 |
1976070.00 |
1963720.67 |
1963720.67 |
0.01 |
0.96 |
|
01/12/2016 |
2047885.00 |
1959965.00 |
1931993.01 |
1931993.01 |
0.01 |
0.96 |
|
01/11/2016 |
2047885.00 |
1923750.00 |
1900265.36 |
1900265.36 |
0.01 |
0.94 |
|
01/10/2016 |
2047885.00 |
1896935.00 |
1867420.95 |
1867420.95 |
0.02 |
0.93 |
|
01/09/2016 |
2047885.00 |
1851115.00 |
1817997.66 |
1817997.66 |
0.02 |
0.90 |
|
01/08/2016 |
2047885.00 |
1805335.00 |
1764825.21 |
1764825.21 |
0.02 |
0.88 |
|
01/07/2016 |
2047885.00 |
1766945.00 |
1716921.47 |
1716921.47 |
0.03 |
0.86 |
|
01/06/2016 |
2047885.00 |
1715845.00 |
1660415.76 |
1660415.76 |
0.03 |
0.84 |
|
01/05/2016 |
2047885.00 |
1664415.00 |
1595743.72 |
1595743.72 |
0.04 |
0.81 |
|
01/04/2016 |
2047885.00 |
1575955.00 |
1533958.24 |
1533958.24 |
0.03 |
0.77 |
|
01/03/2016 |
2047885.00 |
1474525.00 |
1469682.48 |
1469682.48 |
0.00 |
0.72 |