Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)
Budget at completion: 849349,00
Start Date: 14/01/2013
End Date: 30/06/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/06/2016 |
849349.00 |
849349.00 |
849349.00 |
849349.00 |
0.00 |
1.00 |
|
01/05/2016 |
849349.00 |
844848.00 |
844975.24 |
844975.24 |
0.00 |
0.99 |
|
01/04/2016 |
849349.00 |
830541.25 |
840601.47 |
840601.47 |
-0.01 |
0.98 |
|
01/03/2016 |
849349.00 |
828290.75 |
836426.52 |
836426.52 |
-0.01 |
0.98 |
|
01/02/2016 |
849349.00 |
826040.25 |
830851.99 |
830851.99 |
-0.01 |
0.97 |
|
01/01/2016 |
849349.00 |
820414.00 |
825762.19 |
825762.19 |
-0.01 |
0.97 |
|
01/12/2015 |
849349.00 |
814787.75 |
820672.40 |
820672.40 |
-0.01 |
0.96 |
|
01/11/2015 |
849349.00 |
785049.00 |
849349.00 |
849349.00 |
-0.08 |
0.92 |
|
01/10/2015 |
849349.00 |
768491.75 |
780362.15 |
780362.15 |
-0.02 |
0.90 |
|
01/09/2015 |
849349.00 |
775404.00 |
849349.00 |
849349.00 |
-0.09 |
0.91 |
|
01/08/2015 |
849349.00 |
783280.75 |
791166.86 |
791166.86 |
-0.01 |
0.92 |
|
01/07/2015 |
849349.00 |
783280.75 |
778271.87 |
778271.87 |
0.01 |
0.92 |
|
01/06/2015 |
849349.00 |
776529.25 |
764148.77 |
764148.77 |
0.02 |
0.91 |
|
01/05/2015 |
849349.00 |
769777.75 |
750639.73 |
750639.73 |
0.03 |
0.91 |
|
01/04/2015 |
849349.00 |
718659.25 |
737744.74 |
737744.74 |
-0.03 |
0.85 |
|
01/03/2015 |
849349.00 |
704674.00 |
724235.68 |
724235.68 |
-0.03 |
0.83 |
|
01/02/2015 |
849349.00 |
693743.00 |
706544.68 |
706544.68 |
-0.02 |
0.82 |
|
01/01/2015 |
849349.00 |
685384.00 |
693059.19 |
693059.19 |
-0.01 |
0.81 |
|
01/12/2014 |
849349.00 |
659664.00 |
677395.76 |
677395.76 |
-0.03 |
0.78 |
|
01/11/2014 |
849349.00 |
643589.00 |
647292.27 |
647292.27 |
-0.01 |
0.76 |