Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 2384000,00
Start Date: 01/01/2010
End Date: 29/02/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/05/2016 2384000.00 2384000.00 2384000.00 2384000.00 0.00 1.00
01/04/2016 2384000.00 2378500.00 2384000.00 2384000.00 0.00 1.00
01/03/2016 2384000.00 2378500.00 2384000.00 2384000.00 0.00 1.00
01/02/2016 2384000.00 2375000.00 2384000.00 2384000.00 0.00 1.00
01/01/2016 2384000.00 2372750.00 2380499.99 2380499.99 0.00 1.00
01/12/2015 2384000.00 2365200.00 2376999.99 2376999.99 0.00 0.99
01/11/2015 2384000.00 2327150.00 2337917.63 2337917.63 0.00 0.98
01/10/2015 2384000.00 2287600.00 2306900.39 2306900.39 -0.01 0.96
01/09/2015 2384000.00 2253050.00 2264850.56 2264850.56 -0.01 0.95
01/08/2015 2384000.00 2219600.00 2227467.42 2227467.42 0.00 0.93
01/07/2015 2384000.00 2182100.00 2193003.23 2193003.23 0.00 0.92
01/06/2015 2384000.00 2149750.00 2152701.15 2152701.15 0.00 0.90
01/05/2015 2384000.00 2117750.00 2106876.13 2106876.13 0.01 0.89
01/04/2015 2384000.00 2072350.00 2063134.12 2063134.12 0.00 0.87
01/03/2015 2384000.00 1984000.00 2017309.10 2017309.10 -0.02 0.83
01/02/2015 2384000.00 1952000.00 1971484.09 1971484.09 -0.01 0.82
01/01/2015 2384000.00 1916000.00 1929825.02 1929825.02 -0.01 0.80
01/12/2014 2384000.00 1834000.00 1884000.00 1884000.00 -0.03 0.77
01/11/2014 2384000.00 1797000.00 1835397.06 1835397.06 -0.02 0.75
01/10/2014 2384000.00 1756000.00 1793133.61 1793133.61 -0.02 0.74