Earned Value Analysis for the "Action" Level (Data updated on: 05/07/2017)
Budget at completion: 1464563,00
Start Date: 01/07/2010
End Date: 31/10/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/10/2016 |
1464563.00 |
1464563.00 |
1464563.00 |
1464563.00 |
0.00 |
1.00 |
|
01/09/2016 |
1464563.00 |
1418505.50 |
1442759.52 |
1442759.52 |
-0.02 |
0.97 |
|
01/08/2016 |
1464563.00 |
1375236.15 |
1410092.83 |
1410092.83 |
-0.02 |
0.94 |
|
01/07/2016 |
1464563.00 |
1339872.35 |
1425924.13 |
1425924.13 |
-0.06 |
0.91 |
|
01/06/2016 |
1464563.00 |
1339872.35 |
1342151.55 |
1342151.55 |
0.00 |
0.91 |
|
01/05/2016 |
1464563.00 |
1313951.75 |
1306459.00 |
1306459.00 |
0.01 |
0.90 |
|
01/04/2016 |
1464563.00 |
1250268.35 |
1267076.08 |
1267076.08 |
-0.01 |
0.85 |
|
01/03/2016 |
1464563.00 |
1206902.90 |
1228781.63 |
1228781.63 |
-0.02 |
0.82 |
|
01/02/2016 |
1464563.00 |
1188737.00 |
1193070.80 |
1193070.80 |
0.00 |
0.81 |
|
01/01/2016 |
1464563.00 |
1165019.30 |
1178791.15 |
1178791.15 |
-0.01 |
0.80 |
|
01/12/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/11/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/10/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/09/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/08/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/07/2015 |
1464563.00 |
1164608.00 |
1164608.00 |
1164608.00 |
0.00 |
0.80 |
|
01/06/2015 |
1464563.00 |
1163748.00 |
1162438.07 |
1162438.07 |
0.00 |
0.79 |
|
01/05/2015 |
1464563.00 |
1148304.90 |
1157150.70 |
1157150.70 |
-0.01 |
0.78 |
|
01/04/2015 |
1464563.00 |
1137712.20 |
1151163.97 |
1151163.97 |
-0.01 |
0.78 |
|
01/03/2015 |
1464563.00 |
1132311.95 |
1140732.98 |
1140732.98 |
-0.01 |
0.77 |