Earned Value Analysis for the "Action" Level (Data updated on: 13/07/2016)

Budget at completion: 639838,00
Start Date: 19/12/2011
End Date: 30/06/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/02/2013 639838.00 226899.60 226815.05 226815.05 0.00 0.46
01/01/2013 639838.00 206599.80 206537.58 206537.58 0.00 0.42
01/12/2012 639838.00 173424.60 172998.45 172998.45 0.00 0.35
01/11/2012 639838.00 142319.40 142375.77 142375.77 0.00 0.29
01/10/2012 639838.00 110179.20 110294.86 110294.86 0.00 0.23
01/09/2012 639838.00 102313.20 102274.21 102274.21 0.00 0.21
01/08/2012 639838.00 95192.40 95299.74 95299.74 0.00 0.19
01/07/2012 639838.00 87022.80 87279.08 87279.08 0.00 0.18
01/06/2012 639838.00 79598.40 79607.16 79607.16 0.00 0.16
01/05/2012 639838.00 72477.60 72283.96 72283.96 0.00 0.15
01/04/2012 639838.00 64308.00 64263.31 64263.31 0.00 0.13
01/03/2012 639838.00 57187.20 56940.11 56940.11 0.00 0.12
01/02/2012 639838.00 49321.20 49268.19 49268.19 0.00 0.10
01/01/2012 639838.00 25557.60 25677.68 25677.68 0.00 0.05
01/12/2011 639838.00 910.80 963.81 963.81 -0.06 0.00