Earned Value Analysis for the "Action" Level (Data updated on: 01/06/2015)

Budget at completion: 359834,00
Start Date: 16/01/2012
End Date: 07/12/2012
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/12/2012 359834.00 359834.00 359834.00 359834.00 0.00 1.00
01/11/2012 359834.00 356497.41 356562.84 356562.84 0.00 0.99
01/10/2012 359834.00 337655.49 337590.07 337590.07 0.00 0.94
01/09/2012 359834.00 291204.02 291002.30 291002.30 0.00 0.81
01/08/2012 359834.00 268239.80 268239.80 268239.80 0.00 0.75
01/07/2012 359834.00 250837.04 250837.04 250837.04 0.00 0.70
01/06/2012 359834.00 201180.50 201180.50 201180.50 0.00 0.56
01/05/2012 359834.00 167487.00 167487.00 167487.00 0.00 0.47
01/04/2012 359834.00 114361.90 114361.90 114361.90 0.00 0.32
01/03/2012 359834.00 78711.95 78743.28 78743.28 0.00 0.22
01/02/2012 359834.00 64770.20 64770.20 64770.20 0.00 0.18
01/01/2012 359834.00 26850.24 26931.13 26931.13 0.00 0.07