4.2.4. European Federated Interoperability Repository (EFIR)

Earned Value Analysis for the "Action" Level (Data updated on: 05/07/2017)

Budget at completion: 1143887,50
Start Date: 02/01/2013
End Date: 02/05/2105
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/06/2013 1143887.50 94774.25 114380.41 114380.41 -0.17 0.08
01/05/2013 1143887.50 93057.69 98072.91 98072.91 -0.05 0.08
01/04/2013 1143887.50 75281.50 76825.59 76825.59 -0.02 0.07
01/03/2013 1143887.50 56659.10 63938.30 63938.30 -0.11 0.05
01/02/2013 1143887.50 27406.21 40283.63 40283.63 -0.32 0.02
01/01/2013 1143887.50 12579.00 14402.30 14402.30 -0.13 0.01