Earned Value Analysis for the "Action" Level (Data updated on: 06/07/2017)

Budget at completion: 1917824,58
Start Date: 05/11/2010
End Date: 28/04/2017
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/04/2017 1917824.58 1917824.58 1917824.58 1917824.58 0.00 1.00
01/03/2017 1917824.58 1907824.58 1910939.33 1910939.33 0.00 0.99
01/02/2017 1917824.58 1897824.58 1903726.22 1903726.22 0.00 0.99
01/01/2017 1917824.58 1897824.58 1897824.58 1897824.58 0.00 0.99
01/12/2016 1917824.58 1897824.58 1897824.58 1897824.58 0.00 0.99
01/11/2016 1917824.58 1865806.84 1897824.58 1897824.58 -0.02 0.97
01/10/2016 1917824.58 1865806.84 1897824.58 1897824.58 -0.02 0.97
01/09/2016 1917824.58 1822334.64 1897824.58 1897824.58 -0.04 0.95
01/08/2016 1917824.58 1807305.70 1878144.53 1878144.53 -0.04 0.94
01/07/2016 1917824.58 1786518.28 1856252.87 1856252.87 -0.04 0.93
01/06/2016 1917824.58 1765987.05 1836264.83 1836264.83 -0.04 0.92
01/05/2016 1917824.58 1695193.55 1792824.99 1792824.99 -0.05 0.88
01/04/2016 1917824.58 1670039.74 1744961.51 1744961.51 -0.04 0.87
01/03/2016 1917824.58 1637380.34 1697370.49 1697370.49 -0.04 0.85
01/02/2016 1917824.58 1594938.59 1636002.41 1636002.41 -0.03 0.83
01/01/2016 1917824.58 1565553.87 1593810.15 1593810.15 -0.02 0.82
01/12/2015 1917824.58 1531765.00 1556316.27 1556316.27 -0.02 0.80
01/11/2015 1917824.58 1530515.00 1536748.50 1536748.50 0.00 0.80
01/10/2015 1917824.58 1440331.00 1505581.00 1505581.00 -0.04 0.75
01/09/2015 1917824.58 1382071.20 1470807.59 1470807.59 -0.06 0.72