Earned Value Analysis for the "Action" Level (Data updated on: 19/10/2017)
Budget at completion: 474498,00
Start Date: 10/10/2012
End Date: 14/04/2017
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/07/2017 |
474498.00 |
474498.00 |
474498.00 |
474498.00 |
0.00 |
1.00 |
|
01/06/2017 |
474498.00 |
473502.39 |
474498.00 |
474498.00 |
0.00 |
1.00 |
|
01/05/2017 |
474498.00 |
470511.10 |
474498.00 |
474498.00 |
-0.01 |
0.99 |
|
01/04/2017 |
474498.00 |
470511.10 |
474498.00 |
474498.00 |
-0.01 |
0.99 |
|
01/03/2017 |
474498.00 |
470511.10 |
472805.28 |
472805.28 |
0.00 |
0.99 |
|
01/02/2017 |
474498.00 |
455654.06 |
466935.22 |
466935.22 |
-0.02 |
0.96 |
|
01/01/2017 |
474498.00 |
455654.06 |
461830.83 |
461830.83 |
-0.01 |
0.96 |
|
01/12/2016 |
474498.00 |
455654.06 |
456216.00 |
456216.00 |
0.00 |
0.96 |
|
01/11/2016 |
474498.00 |
432099.67 |
449494.71 |
449494.71 |
-0.04 |
0.91 |
|
01/10/2016 |
474498.00 |
432099.67 |
441449.59 |
441449.59 |
-0.02 |
0.91 |
|
01/09/2016 |
474498.00 |
408497.17 |
426546.18 |
426546.18 |
-0.04 |
0.86 |
|
01/08/2016 |
474498.00 |
395695.07 |
412563.85 |
412563.85 |
-0.04 |
0.83 |
|
01/07/2016 |
474498.00 |
393853.37 |
403576.22 |
403576.22 |
-0.02 |
0.83 |
|
01/06/2016 |
474498.00 |
393853.37 |
395370.15 |
395370.15 |
0.00 |
0.83 |
|
01/05/2016 |
474498.00 |
391044.17 |
386773.30 |
386773.30 |
0.01 |
0.82 |
|
01/04/2016 |
474498.00 |
388100.15 |
379334.12 |
379334.12 |
0.02 |
0.82 |
|
01/03/2016 |
474498.00 |
380867.00 |
374039.63 |
374039.63 |
0.02 |
0.80 |
|
01/02/2016 |
474498.00 |
373147.75 |
368240.92 |
368240.92 |
0.01 |
0.79 |
|
01/01/2016 |
474498.00 |
361174.00 |
361338.44 |
361338.44 |
0.00 |
0.76 |
|
01/12/2015 |
474498.00 |
361174.00 |
361174.00 |
361174.00 |
0.00 |
0.76 |