4.2.2. Community building and effective use of the collaborative platforms

Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 3547438,30
Start Date: 16/12/2010
End Date: 31/07/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/07/2016 3547438.30 3547438.30 3547438.30 3547438.30 0.00 1.00
01/06/2016 3547438.30 3547034.70 3517462.42 3517462.42 0.01 1.00
01/05/2016 3547438.30 3475383.63 3460536.69 3460536.69 0.00 0.98
01/04/2016 3547438.30 3405325.96 3403992.16 3403992.16 0.00 0.96
01/03/2016 3547438.30 3350758.79 3348056.00 3348056.00 0.00 0.94
01/02/2016 3547438.30 3297846.56 3290136.07 3290136.07 0.00 0.93
01/01/2016 3547438.30 3222409.22 3234164.70 3234164.70 0.00 0.91
01/12/2015 3547438.30 3146883.76 3178193.25 3178193.25 -0.01 0.88
01/11/2015 3547438.30 3121875.31 3118997.83 3118997.83 0.00 0.88
01/10/2015 3547438.30
01/09/2015 3547438.30 3004492.17 3004459.68 3004459.68 0.00 0.84
01/08/2015 3547438.30 2884751.13 2935624.00 2935624.00 -0.02 0.81
01/07/2015 3547438.30 2847114.60 2914057.48 2914057.48 -0.02 0.80
01/06/2015 3547438.30 2779924.53 2866718.51 2866718.51 -0.03 0.78
01/05/2015 3547438.30 2722815.45 2813430.59 2813430.59 -0.03 0.77
01/04/2015 3547438.30 2637308.84 2762564.70 2762564.70 -0.05 0.74
01/03/2015 3547438.30 2607478.65 2709276.81 2709276.81 -0.04 0.73
01/02/2015 3547438.30 2542944.94 2655988.86 2655988.86 -0.04 0.72
01/01/2015 3547438.30 2491326.56 2607545.28 2607545.28 -0.04 0.70
01/12/2014 3547438.30 2458708.27 2554185.29 2554185.29 -0.04 0.69