4.2.1. Integrated Collaborative Platform - Joinup

Estimate at Completion (Data updated on: 04/07/2017)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
02/2013 3849413.13 3810919.00
01/2013 3849413.13 3810919.00
12/2012 3773187.13 3810919.00
11/2012 3773187.13 3810919.00
10/2012 3773187.13 3810919.00
09/2012 3773187.13 3810919.00
08/2012 3773187.13 3810919.00
07/2012 3736195.10 3810919.00
06/2012 3736195.10 3810919.00
03/2012 3699921.36 3810919.00
02/2012 3773187.13 3810919.00
01/2012 3773187.13 3810919.00
12/2011 3810919.00 3810919.00
11/2011 3810919.00 3810919.00
10/2011 3810919.00 3810919.00
09/2011 3810919.00 3810919.00
07/2011 3810919.00 3810919.00
06/2011 3810919.00 3810919.00
05/2011 3810919.00 3810919.00
04/2011 3810919.00 3810919.00