Earned Value Analysis for the "Action" Level (Data updated on: 05/07/2017)
Budget at completion: 2290000,00
Start Date: 01/07/2010
End Date: 31/12/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/11/2016 |
2290000.00 |
2290000.00 |
2270458.46 |
2270458.46 |
0.01 |
1.00 |
|
01/10/2016 |
2290000.00 |
2285000.00 |
2250916.92 |
2250916.92 |
0.02 |
1.00 |
|
01/09/2016 |
2290000.00 |
2280000.00 |
2232263.62 |
2232263.62 |
0.02 |
1.00 |
|
01/08/2016 |
2290000.00 |
2270000.00 |
2212722.06 |
2212722.06 |
0.03 |
0.99 |
|
01/07/2016 |
2290000.00 |
2203000.00 |
2192292.27 |
2192292.27 |
0.00 |
0.96 |
|
01/06/2016 |
2290000.00 |
2203000.00 |
2173638.98 |
2173638.98 |
0.01 |
0.96 |
|
01/05/2016 |
2290000.00 |
2173000.00 |
2149890.94 |
2149890.94 |
0.01 |
0.95 |
|
01/04/2016 |
2290000.00 |
2096000.00 |
2126142.87 |
2126142.87 |
-0.01 |
0.92 |
|
01/03/2016 |
2290000.00 |
2015000.00 |
2091714.26 |
2091714.26 |
-0.04 |
0.88 |
|
01/02/2016 |
2290000.00 |
1976500.00 |
2054006.79 |
2054006.79 |
-0.04 |
0.86 |
|
01/01/2016 |
2290000.00 |
1965000.00 |
2019578.19 |
2019578.19 |
-0.03 |
0.86 |
|
01/12/2015 |
2290000.00 |
1944000.00 |
1985149.59 |
1985149.59 |
-0.02 |
0.85 |
|
01/11/2015 |
2290000.00 |
1934000.00 |
1947442.08 |
1947442.08 |
-0.01 |
0.84 |
|
01/10/2015 |
2290000.00 |
1880900.00 |
1913013.48 |
1913013.48 |
-0.02 |
0.82 |
|
01/09/2015 |
2290000.00 |
1875900.00 |
1860836.65 |
1860836.65 |
0.01 |
0.82 |
|
01/08/2015 |
2290000.00 |
1784500.00 |
1808659.83 |
1808659.83 |
-0.01 |
0.78 |
|
01/07/2015 |
2290000.00 |
1689600.00 |
1777507.96 |
1777507.96 |
-0.05 |
0.74 |
|
01/05/2015 |
2290000.00 |
1684000.00 |
1710753.97 |
1710753.97 |
-0.02 |
0.74 |
|
01/04/2015 |
2290000.00 |
1678000.00 |
1679602.10 |
1679602.10 |
0.00 |
0.73 |
|
01/03/2015 |
2290000.00 |
1664000.00 |
1646966.81 |
1646966.81 |
0.01 |
0.73 |