Earned Value Analysis for the "Action" Level (Data updated on: 12/02/2018)
Budget at completion: 2462460,00
Start Date: 19/06/2012
End Date: 31/12/2017
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/12/2017 |
2462460.00 |
2462460.00 |
2462460.00 |
2462460.00 |
0.00 |
1.00 |
|
01/09/2017 |
2462460.00 |
2452096.00 |
2454073.37 |
2454073.37 |
0.00 |
1.00 |
|
01/08/2017 |
2462460.00 |
2423523.80 |
2451363.84 |
2451363.84 |
-0.01 |
0.98 |
|
01/07/2017 |
2462460.00 |
2423523.80 |
2448396.27 |
2448396.27 |
-0.01 |
0.98 |
|
01/06/2017 |
2462460.00 |
2423523.80 |
2445686.74 |
2445686.74 |
-0.01 |
0.98 |
|
01/05/2017 |
2462460.00 |
2393208.65 |
2437925.29 |
2437925.29 |
-0.02 |
0.97 |
|
01/04/2017 |
2462460.00 |
2393208.65 |
2429811.04 |
2429811.04 |
-0.02 |
0.97 |
|
01/03/2017 |
2462460.00 |
2393208.65 |
2422755.18 |
2422755.18 |
-0.01 |
0.97 |
|
01/02/2017 |
2462460.00 |
2383288.05 |
2414640.94 |
2414640.94 |
-0.01 |
0.97 |
|
01/01/2017 |
2462460.00 |
2344011.25 |
2407585.07 |
2407585.07 |
-0.03 |
0.95 |
|
01/12/2016 |
2462460.00 |
2292977.35 |
2399823.62 |
2399823.62 |
-0.04 |
0.93 |
|
01/11/2016 |
2462460.00 |
2244402.05 |
2373461.00 |
2373461.00 |
-0.05 |
0.91 |
|
01/10/2016 |
2462460.00 |
2244402.05 |
2343424.06 |
2343424.06 |
-0.04 |
0.91 |
|
01/09/2016 |
2462460.00 |
2181223.75 |
2314752.41 |
2314752.41 |
-0.06 |
0.89 |
|
01/08/2016 |
2462460.00 |
2138744.60 |
2244684.04 |
2244684.04 |
-0.05 |
0.87 |
|
01/07/2016 |
2462460.00 |
2095693.75 |
2171430.74 |
2171430.74 |
-0.03 |
0.85 |
|
01/06/2016 |
2462460.00 |
1983933.00 |
2103173.36 |
2103173.36 |
-0.06 |
0.81 |
|
01/05/2016 |
2462460.00 |
1911781.85 |
2024937.79 |
2024937.79 |
-0.06 |
0.78 |
|
01/04/2016 |
2462460.00 |
1863782.30 |
1946702.21 |
1946702.21 |
-0.04 |
0.76 |
|
01/03/2016 |
2462460.00 |
1811641.90 |
1872022.81 |
1872022.81 |
-0.03 |
0.74 |