Earned Value Analysis for the "Action" Level (Data updated on: 01/06/2015)

Budget at completion: 100000,00
Start Date: 27/07/2011
End Date: 31/01/2012
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/01/2012 100000.00 100000.00 100000.00 100000.00 0.00 1.00
01/12/2011 100000.00 88000.00 87844.83 87844.83 0.00 0.88
01/11/2011 100000.00 74300.00 74766.57 74766.57 -0.01 0.74
01/10/2011 100000.00 63650.00 61688.32 61688.32 0.03 0.64
01/09/2011 100000.00 49500.00 48979.59 48979.59 0.01 0.50
01/08/2011 100000.00 16800.00 26530.61 26530.61 -0.37 0.17
01/07/2011 100000.00 2700.00 3061.22 3061.22 -0.12 0.03