Earned Value Analysis for the "Action" Level (Data updated on: 01/06/2015)

Budget at completion: 799998,00
Start Date: 16/05/2011
End Date: 13/12/2013
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/04/2014 799998.00 799998.00 799998.00 799998.00 0.00 1.00
01/03/2014 799998.00 799998.00 799998.00 799998.00 0.00 1.00
01/02/2014 799998.00 792355.90 799998.00 799998.00 -0.01 0.99
01/01/2014 799998.00 776840.11 799998.00 799998.00 -0.03 0.97
01/12/2013 799998.00 762366.43 799998.00 799998.00 -0.05 0.95
01/11/2013 799998.00 755129.58 788419.06 788419.06 -0.04 0.94
01/10/2013 799998.00 747892.74 762995.72 762995.72 -0.02 0.93
01/09/2013 799998.00 740945.37 740816.72 740816.72 0.00 0.93
01/08/2013 799998.00 727398.00 727307.95 727307.95 0.00 0.91
01/07/2013 799998.00 706208.53 713155.90 713155.90 -0.01 0.88
01/06/2013 799998.00 676871.07 676871.07 676871.07 0.00 0.85
01/05/2013 799998.00 649713.79 649889.17 649889.17 0.00 0.81
01/04/2013 799998.00 627903.88 628127.71 628127.71 0.00 0.78
01/03/2013 799998.00 619009.76 618836.61 618836.61 0.00 0.77
01/02/2013 799998.00 627254.97 609967.84 609967.84 0.03 0.78
01/01/2013 799998.00 589232.46 599434.45 599434.45 -0.02 0.74
01/12/2012 799998.00 584873.56 579968.18 579968.18 0.01 0.73
01/11/2012 799998.00 564606.54 563085.29 563085.29 0.00 0.71
01/10/2012 799998.00 558379.48 558341.68 558341.68 0.00 0.70
01/09/2012 799998.00 556025.76 553382.46 553382.46 0.00 0.70