Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)
Budget at completion: 1674921,00
Start Date: 15/06/2011
End Date: 15/05/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/08/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/07/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/06/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/05/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/04/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/03/2012 |
1674921.00 |
199921.00 |
199921.00 |
199921.00 |
0.00 |
0.12 |
|
01/02/2012 |
1674921.00 |
196006.00 |
185602.92 |
185602.92 |
0.06 |
0.12 |
|
01/01/2012 |
1674921.00 |
188176.00 |
158268.41 |
158268.41 |
0.19 |
0.11 |
|
01/12/2011 |
1674921.00 |
129116.00 |
129632.26 |
129632.26 |
0.00 |
0.08 |
|
01/11/2011 |
1674921.00 |
113456.00 |
110702.59 |
110702.59 |
0.02 |
0.07 |
|
01/10/2011 |
1674921.00 |
93881.00 |
93563.57 |
93563.57 |
0.00 |
0.06 |
|
01/09/2011 |
1674921.00 |
63543.70 |
82453.43 |
82453.43 |
-0.23 |
0.04 |
|
01/08/2011 |
1674921.00 |
48485.96 |
58867.40 |
58867.40 |
-0.18 |
0.03 |
|
01/07/2011 |
1674921.00 |
26097.47 |
27519.14 |
27519.14 |
-0.05 |
0.02 |
|
01/06/2011 |
1674921.00 |
9676.59 |
10006.96 |
10006.96 |
-0.03 |
0.01 |