1.7. e-PRIOR

Estimate at Completion (Data updated on: 23/03/2016)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
03/2011 11197916.67 10750000.00
02/2011 11197916.67 10750000.00
01/2011 11197916.67 10750000.00
12/2010 11082474.23 10750000.00
11/2010 11082474.23 10750000.00
10/2010 10969387.76 10750000.00
09/2010 10750000.00 10750000.00
08/2010 10858585.86 10750000.00
07/2010 10539215.69 10750000.00