1.6. Common Infrastructure for Public Administrations

Estimate at Completion (Data updated on: 01/06/2015)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
04/2015 2270000.00 2270000.00
03/2015 2292929.29 2270000.00
02/2015 2270000.00 2270000.00
01/2015 2292929.29 2270000.00
12/2014 2316326.53 2270000.00
11/2014 2316326.53 2270000.00
10/2014 2316326.53 2270000.00
09/2014 2292929.29 2270000.00
08/2014 2292929.29 2270000.00
07/2014 2292929.29 2270000.00
06/2014 2292929.29 2270000.00
05/2014 2270000.00 2270000.00
04/2014 2270000.00 2270000.00
03/2014 2270000.00 2270000.00
02/2014 2270000.00 2270000.00
01/2014 2270000.00 2270000.00
12/2013 2270000.00 2270000.00
11/2013 2270000.00 2270000.00
10/2013 2270000.00 2270000.00
09/2013 2270000.00 2270000.00