Budget at completion: 2270000,00
Start Date: 30/11/2010
End Date: 30/04/2015
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/04/2015 2270000.00 2270000.00 2270000.00 2270000.00 0.00 1.00
01/03/2015 2270000.00 2213000.00 2225232.55 2225232.55 -0.01 0.97
01/02/2015 2270000.00 2178250.00 2180465.12 2180465.12 0.00 0.96
01/01/2015 2270000.00 2126550.00 2139767.45 2139767.45 -0.01 0.94
01/12/2014 2270000.00 2050000.00 2095000.00 2095000.00 -0.02 0.90
01/11/2014 2270000.00 2019200.00 2061072.80 2061072.80 -0.02 0.89
01/10/2014 2270000.00 1984550.00 2020320.87 2020320.87 -0.02 0.87
01/09/2014 2270000.00 1953750.00 1979007.31 1979007.31 -0.01 0.86
01/08/2014 2270000.00 1920240.00 1939888.54 1939888.54 -0.01 0.85
01/07/2014 2270000.00 1884520.00 1902547.88 1902547.88 -0.01 0.83
01/06/2014 2270000.00 1851520.00 1861651.00 1861651.00 -0.01 0.82
01/05/2014 2270000.00 1820420.00 1824310.34 1824310.34 0.00 0.80
01/04/2014 2270000.00 1775470.00 1780191.56 1780191.56 0.00 0.78
01/03/2014 2270000.00 1735320.00 1739669.28 1739669.28 0.00 0.76
01/02/2014 2270000.00 1692020.00 1700402.82 1700402.82 0.00 0.75
01/01/2014 2270000.00 1655540.00 1663006.14 1663006.14 0.00 0.73
01/12/2013 2270000.00 1620000.00 1620000.00 1620000.00 0.00 0.71
01/11/2013 2270000.00 1567500.00 1568787.55 1568787.55 0.00 0.69
01/10/2013 2270000.00 1517000.00 1519902.95 1519902.95 0.00 0.67
01/09/2013 2270000.00 1464500.00 1466362.67 1466362.67 0.00 0.65