Earned Value Analysis for the "Action" Level (Data updated on: 16/02/2016)

Budget at completion: 250000,00
Start Date: 31/12/2014
End Date: 18/12/2015
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/01/2016 250000.00 250000.00 250000.00 250000.00 0.00 1.00
01/12/2015 250000.00 248750.00 250000.00 250000.00 -0.01 1.00
01/11/2015 250000.00 227500.00 240833.33 240833.33 -0.06 0.91
01/10/2015 250000.00 187500.00 209086.10 209086.10 -0.10 0.75
01/09/2015 250000.00 163000.00 175827.11 175827.11 -0.07 0.65