2.16. European Single Procurement Document Service

Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 150000,00
Start Date: 01/12/2014
End Date: 30/06/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/06/2016 150000.00 150000.00 150000.00 150000.00 0.00 1.00
01/05/2016 150000.00 146000.00 145000.00 145000.00 0.01 0.97
01/04/2016 150000.00 138000.00 140000.00 140000.00 -0.01 0.92
01/03/2016 150000.00 136000.00 135227.27 135227.27 0.01 0.91
01/02/2016 150000.00 115000.00 130000.00 130000.00 -0.12 0.77
01/01/2016 150000.00 105000.00 114000.00 114000.00 -0.08 0.70
01/12/2015 150000.00 103000.00 105000.00 105000.00 -0.02 0.69
01/11/2015 150000.00 97000.00 103055.56 103055.56 -0.06 0.65
01/10/2015 150000.00 81000.00 97222.22 97222.22 -0.17 0.54
01/09/2015 150000.00 66000.00 84341.88 84341.88 -0.22 0.44