2.18. Participatory Knowledge for Supporting Decision Making

Earned Value Analysis for the "Action" Level (Data updated on: 04/07/2017)

Budget at completion: 527528,00
Start Date: 29/05/2015
End Date: 31/07/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/07/2016 527528.00 527528.00 527528.00 527528.00 0.00 1.00
01/06/2016 527528.00 525928.00 511046.94 511046.94 0.03 1.00
01/05/2016 527528.00 493820.95 493781.07 493781.07 0.00 0.94
01/04/2016 527528.00 421931.50 429972.07 429972.07 -0.02 0.80
01/03/2016 527528.00 327527.85 335989.95 335989.95 -0.03 0.62
01/02/2016 527528.00 281793.10 255032.68 255032.68 0.10 0.53
01/01/2016 527528.00 245422.40 184794.73 184794.73 0.33 0.47
01/12/2015 527528.00 205889.85 150816.63 150816.63 0.37 0.43
01/11/2015 527528.00 147692.35 108141.49 108141.49 0.37 0.28
01/10/2015 527528.00 74373.85 66732.09 66732.09 0.11 0.16
01/09/2015 527528.00 10149.25 17638.84 17638.84 -0.42 0.02