1.22. Big Data and Open Knowledge for Public Administration

Earned Value Analysis for the "Action" Level (Data updated on: 15/07/2016)

Budget at completion: 297712,00
Start Date: 26/08/2015
End Date: 16/05/2016
Covered period Budget at Completion (Euro) Earned Value (Euro) Planned Value (Euro) Actual Cost (Euro) % of Budget Deviation % of Completion
01/06/2016 297712.00 297712.00 297712.00 297712.00 0.00 1.00
01/05/2016 297712.00 292007.30 297712.00 297712.00 -0.02 0.98
01/04/2016 297712.00 259684.40 289684.06 289684.06 -0.10 0.87
01/03/2016 297712.00 224290.35 273154.57 273154.57 -0.18 0.75
01/02/2016 297712.00 190791.35 245512.24 245512.24 -0.22 0.64
01/01/2016 297712.00 162221.30 220273.55 220273.55 -0.26 0.54
01/12/2015 297712.00 137566.00 195342.69 195342.69 -0.30 0.46
01/11/2015 297712.00 104949.70 127742.26 127742.26 -0.18 0.35
01/10/2015 297712.00 48901.10 78255.92 78255.92 -0.38 0.16
01/09/2015 297712.00 17906.10 34930.87 34930.87 -0.49 0.06