Earned Value Analysis for the "Action" Level (Data updated on: 15/07/2016)
Budget at completion: 297712,00
Start Date: 26/08/2015
End Date: 16/05/2016
|
Covered period |
Budget at Completion (Euro) |
Earned Value (Euro) |
Planned Value (Euro) |
Actual Cost (Euro) |
% of Budget Deviation |
% of Completion |
|
01/06/2016 |
297712.00 |
297712.00 |
297712.00 |
297712.00 |
0.00 |
1.00 |
|
01/05/2016 |
297712.00 |
292007.30 |
297712.00 |
297712.00 |
-0.02 |
0.98 |
|
01/04/2016 |
297712.00 |
259684.40 |
289684.06 |
289684.06 |
-0.10 |
0.87 |
|
01/03/2016 |
297712.00 |
224290.35 |
273154.57 |
273154.57 |
-0.18 |
0.75 |
|
01/02/2016 |
297712.00 |
190791.35 |
245512.24 |
245512.24 |
-0.22 |
0.64 |
|
01/01/2016 |
297712.00 |
162221.30 |
220273.55 |
220273.55 |
-0.26 |
0.54 |
|
01/12/2015 |
297712.00 |
137566.00 |
195342.69 |
195342.69 |
-0.30 |
0.46 |
|
01/11/2015 |
297712.00 |
104949.70 |
127742.26 |
127742.26 |
-0.18 |
0.35 |
|
01/10/2015 |
297712.00 |
48901.10 |
78255.92 |
78255.92 |
-0.38 |
0.16 |
|
01/09/2015 |
297712.00 |
17906.10 |
34930.87 |
34930.87 |
-0.49 |
0.06 |