1.4. ECAS - STORK Integration

Estimate at Completion (Data updated on: 04/07/2017)

Measured period Estimate at Completion (Euro) Budget at Completion (Euro)
02/2013 1968732.04 2027794.00
01/2013 1988033.33 2027794.00
12/2012 2027794.00 2027794.00
11/2012 2027794.00 2027794.00
10/2012 2027794.00 2027794.00
09/2012 2027794.00 2027794.00
08/2012 2027794.00 2027794.00
07/2012 2027794.00 2027794.00
06/2012 2027794.00 2027794.00
05/2012 2027794.00 2027794.00
04/2012 2027794.00 2027794.00
03/2012 2027794.00 2027794.00
02/2012 2027794.00 2027794.00
01/2012 2027794.00 2027794.00
12/2011 2090509.28 2027794.00
11/2011 2112285.42 2027794.00
10/2011 2134520.00 2027794.00
09/2011 2304311.36 2027794.00
08/2011 2278420.22 2027794.00
07/2011 2253104.44 2027794.00