703039867OVERALL STATUS:   YELLOW   

Date:   

Reporting Period:   to  


Project Owner (PO): DG CNECT

Business Manager (BM): Maya Madrid

Solution Provider (SP): DIGIT

Project Manager (PM): Bogdan Dumitriu

Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.8

 

100%

COMPLETED


Domibus 5.1.3

 

 

100%

COMPLETED


Domibus 5.1.4

 

 

20%

IN PROGRESS


Domibus 5.2 RC

Q4 2024

67%

IN PROGRESS

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q4 2024

Q4 2024

0%

NOT STARTED

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q1 2025

Q1 2025

0%

NOT STARTED


Domibus 6.0 RC

Q2 2025

Q3 2025

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

Q4 2025

Q4 2025

0%

NOT STARTED


DomiSML 5.0 RC

0%

NOT STARTED


DomiSML 5.0 FR

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.1 RC

60%

IN PROGRESS


DomiSMP 5.1 FR

0%

NOT STARTED


eDelivery AS4, SMP, BDXL & ebCore Party Id 2.0 profiles

95%

IN PROGRESS

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

A first public consultation was held between July 2023 - November 2023.

A second public consultation was held between 8 March 2024 - 8 April 2024.

The specifications are to be tentatively adopted in July, after live testing during two events planned in June.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

52%

IN PROGRESS


Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile

52%

ON HOLD


Migration to GITLab

Q4 202412%

ON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations

 

100%

COMPLETED

New documentation framework setup and support process implemented. New documentation site created.

  • Go live with the new documentation model pending adjustments in the Domibus release page.
  • Due to the postponing of the Domibus 5.2 release, release for which the premiere of the new documentation format was planned for, it was decided that the new format will be implemented with Domibus 5.0.8 release, once the new Domibus release page structure is validated.


Newsroom account for eDelivery (for mailing list management)

?

10%

CANCELLED

The development of a newsroom account for eDelivery has been suspended.
Update eDelivery projects & stakeholders repository

50%

IN PROGRESS

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
eDelivery FAQ (overhaul of communication materials)

 

 

15%

IN PROGRESS

Updating eDelivery knowledge base and display of FAQ in various contexts.
eDelivery Self-Assessment and Cost-Analysis tools (overhaul of communication materials)

 

 

10%

IN PROGRESS

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Tutorial materials (overhaul of communication materials)

Tbc.

 

0%

NOT STARTED


Conformant solutions presentation 

 

70%

IN PROGRESS

Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. 
Pitch and launch joint Building Blocks social media account

80%

IN PROGRESS

Launch social media accounts together with other Building Blocks.
eDelivery Interoperability Forum 29 February

 

100%

COMPLETE

 
How-to video on DomiSMP 5.0 new features published

 

100%

COMPLETE

 
eDelivery Interoperability Forum 18 April

25%

IN PROGRESS

 
eDelivery Informal Cooperation Network meeting 15 May

10%

IN PROGRESS

 
Interoperability Event 11 & 25 June

15%

IN PROGRESS

 
Webinar on eDelivery value proposition (Member States) 26 September

0%

NOT STARTED

 
How-to video on Domibus new features 24 October

 

 

0%

NOT STARTED

 
eDelivery Interoperability Forum 24 October

 

 

0%

NOT STARTED

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

NOT STARTED

 
Dynamic Discovery Webinar 12 December

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 7 (March 2024)

100%

COMPLETED

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

NOT STARTED

 
eDelivery Informal Cooperation Network meeting 15 May

 

 

5%

IN PROGRESS

 
Interoperability Event 11 June

 

 

0%

NOT STARTED

 
Webinar on eDelivery value proposition (Member States)  26 September

 

 

0%

NOT STARTED

 
How-to video on Domibus new features 24 October

 

 

0%

NOT STARTED

 
eDelivery Interoperability Forum 24 October

 

 

0%

NOT STARTED

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

NOT STARTED

 
Dynamic Discovery Webinar 12 December

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 7 (March 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

NOT STARTED

 

Overall Project Progress

Technical

  • eDelivery 2.0 profiles (2023 drafts):
    • The disposition of public review comments following the consultation on the first drafts (2023) published: AS4 | SMP.
  • eDelivery 2.0 profiles (2024 drafts):
    • Second drafts of the eDelivery profiles published: AS4 | SMP | BDXL | ebCore Party Id.
    • 2nd public consultation (on the 2024 drafts): 8 March – 8 April. Feedback received from one person / organisation.
  • Domibus development:
    • Domibus 5.1.3 security fix release was published on .
    • Domibus 5.0.8 bug fix release published on .
    • Domibus roadmap updated: Domibus 5.2 to be released in Q4 2024, Domibus 6.0 to be released by end of 2025.
  • eDelivery Conformance Testing service:
    • Implementation of test cases for the Pull profile enhancement concluded. Deployment in production to be planned
    • Implementation of test cases for the Dynamic Sender profile enhancement ongoing
    • Analysis to strengthen the testing of the eDelivery Common Profile concluded.
    • Work also ongoing to increase the level of service maturity

Onboarding & Communication

Technical Progress

Specifications: eDelivery AS4 & SMP Profiles

Software product: Domibus

  • Domibus 5.0.8 bug fix released on the  
  • Domibus 5.1.3 bug fix released on the , containing a fix for multitenancy related issue and several library upgrades
  • Domibus 5.1.4 bug fix release, including the fixes implemented in 5.0.8, is planned for the  
  • Domibus 5.2 RC
    • Limited progress due to the effort required for several bug fix releases and the extensive maintenance and support workload. Leaving limited capacity for development tasks, as highlighted in the issue EDELIVERY-11247. Due to the prolonged onset of this dynamic, the eDelivery roadmap had to be revisited:

      • Domibus 5.2 RC - Q4 2024 | Domibus 5.2 FR – Q4 2024

      • Domibus 6.0 RC – Q3 2025 | Domibus 6.0 FR – Q4 2025

  • Domibus new documentation framework
    • The work in defining and implementing the new Domibus documentation framework and supporting processes is concluded. Its go-live has been postponed several times with delays in the Domibus 5.2 release, release which was slated to premiere the new format. It was decided that the new framework will be implemented in the Domibus 5.0.8 release, once the adjustments in Domibus release page are agreed upon and implemented.

Software product: DomiSMP

  • DomiSMP 5.1 RC development activities are ongoing.

Software product: DomiSML

  • DomiSML 4.3 Vulnerability Assessment Report received and analyzed. No major issues detected. Feedback provided to the security team. New version of the report is expected.

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

  • eDelivery AS4 1.15 profile enhancements conformance testing implementation:
    • Implementation of test cases for the Pull profile enhancement concluded. Deployment in production to be planned
    • Implementation of test cases for the Dynamic Sender profile enhancement ongoing
  • Ongoing support being provided to the SW providers testing their solutions

Software product: Docker images

  • Domibus 5.0.8 in a Tomcat + MySQL configuration Docker images for published on the (OOTS).
  • Docker image performance testing concluded

Service: PKI Service

  • N/A

Service: SML Service

  • A renewed collaboration was established with OpenPeppol. eDelivery is now part of the Peppol Critical Infrastructure Working Group, under the framework of which it will participate in a pilot for SML federation, exploring technical options for Peppol to be able to host SML records also outside the eDelivery SML Service.

Section 2: Evolutive Maintenance

Change Requests

KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
EDELGOV-112Well balancing web page DOMIBUS Admin: header takes more place than the body where are messages to monitor

Request for Change

Mar 14, 2024Mar 26, 2024
Marcio SAMPAIOErnest MUTAGANDA

stat

Rejected
EDELGOV-111Provide scripts for scheduled automated updates of PModes or Trust Stores

Request for Change

Nov 15, 2023Feb 6, 2024
Cosmin BACIUPim VAN DER EIJK

REJECTED

Rejected
EDELGOV-92eDelivery growth factor by improved DNS recommendation of SML discovery

Request for Change

Dec 2, 2022Oct 23, 2023
Joze RIHTARSICGunnar Nilsson

UNDER REVIEW

Unresolved
EDELGOV-89Fulfill the requirements on the BDEW AS4 Profile
Request for Change
Oct 28, 2022Sep 22, 2023
Cosmin BACIUSven Uthe

UNDER REVIEW

Unresolved
EDELGOV-76Request for investigation of using multihop functionality with AS4
Request for Change
Nov 12, 2020Sep 28, 2022
Marcio SAMPAIOOle Vilstrup Møller


POSTPONED

On hold
EDELGOV-51Dynamic Service discovery - SML/SMP change request

Request for Change

Sep 28, 2018Sep 22, 2023
Marcio SAMPAIOCIF VSRS

UNDER REVIEW

Unresolved

Release Calendar

Section 3: Support Office

Incident Management

SMT - Workload Details

The volume of opened and handled SMT tickets decreased slightly in December 2023, as a result of the end-of-the-year break. There were still also a lot of questions from users on Domibus migration issues (migration scripts), docker usage, conformance tests issues (Opentext), etc.

Email Interaction

For eDelivery, received emails were related to:

  • Requests for AS4 connectivity test with Everysite LTD, Eufex Deutschand GmbH, Sanmarco Informatica S.P.
  • eDelivery conformance tests- several questions from Opentext that is running the tests with the new GITB platform
  • SGTR and PKI services – SOD finalised
  • Questions from users: Domibus (question on Kerberos DES and RC4, certificate configuration, Domibus migration from 4.2.6 to 5.0.6 (EUCEG), Domibus 5.1.2 and dynamic discovery, integration with AWS secrets manage, Docker), SML/SMP (SMP/SMK certificate update/renewal, DomiSMP 5.0.1 installation issues), updated list of Peppol participants sent to Peppol, PKI certificates (OOTS, UDB, EUDAMED, CixP), TAPAS (ICS2 connectivity test assistance requests (re-directed to the National service desks), onboarding request forwarded to National Helpdesk), question on TLS certificate redirected to ITSM3OPS)
  • There was a total of 641 emails in the FMB. We have removed 64 emails for SML Inconsistency, 42 alerts, 34 xmatters and 11 emails from PKI CommisSign from the count, which makes a total of 490 received mails for the reporting month.

PKI

In December 2023, 10 certificates were issued:1 SGTR, 1 EUDAMED, 1 UDB, 7 OOTS.

Operations Management

SML – Availability

The achieved availability for SML1 was within the target for the month of December.