703039867OVERALL STATUS:   YELLOW   

Date:   

Reporting Period:   to  


Project Owner (PO): DG CNECT

Business Manager (BM): Maya Madrid

Solution Provider (SP): DIGIT

Project Manager (PM): Bogdan Dumitriu

Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.8

 

100%

COMPLETED


Domibus 5.1.3

 

 

100%

COMPLETED


Domibus 5.1.4

 

 

20%

IN PROGRESS


Domibus 5.2 RC

Q4 2024

67%

IN PROGRESS

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q4 2024

Q4 2024

0%

NOT STARTED

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q1 2025

Q1 2025

0%

NOT STARTED


Domibus 6.0 RC

Q2 2025

Q3 2025

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

Q4 2025

Q4 2025

0%

NOT STARTED


DomiSML 5.0 RC

0%

NOT STARTED


DomiSML 5.0 FR

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.1 RC

60%

IN PROGRESS


DomiSMP 5.1 FR

0%

NOT STARTED


eDelivery AS4, SMP, BDXL & ebCore Party Id 2.0 profiles

95%

IN PROGRESS

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

A first public consultation was held between July 2023 - November 2023.

A second public consultation was held between 8 March 2024 - 8 April 2024.

The specifications are to be tentatively adopted in July, after live testing during two events planned in June.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

52%

IN PROGRESS


Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile

52%

ON HOLD


Migration to GITLab

Q4 202412%

ON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations

 

100%

COMPLETED

New documentation framework setup and support process implemented. New documentation site created.

  • Go live with the new documentation model pending adjustments in the Domibus release page.
  • Due to the postponing of the Domibus 5.2 release, release for which the premiere of the new documentation format was planned for, it was decided that the new format will be implemented with Domibus 5.0.8 release, once the new Domibus release page structure is validated.


Newsroom account for eDelivery (for mailing list management)

?

10%

CANCELLED

The development of a newsroom account for eDelivery has been suspended.
Update eDelivery projects & stakeholders repository

50%

IN PROGRESS

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
eDelivery FAQ (overhaul of communication materials)

 

 

15%

IN PROGRESS

Updating eDelivery knowledge base and display of FAQ in various contexts.
eDelivery Self-Assessment and Cost-Analysis tools (overhaul of communication materials)

 

 

10%

IN PROGRESS

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Tutorial materials (overhaul of communication materials)

Tbc.

 

0%

NOT STARTED


Conformant solutions presentation 

 

70%

IN PROGRESS

Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. 
Pitch and launch joint Building Blocks social media account

80%

IN PROGRESS

Launch social media accounts together with other Building Blocks.
eDelivery Interoperability Forum 29 February

 

100%

COMPLETE

 
How-to video on DomiSMP 5.0 new features published

 

100%

COMPLETE

 
eDelivery Interoperability Forum 18 April

25%

IN PROGRESS

 
eDelivery Informal Cooperation Network meeting 15 May

10%

IN PROGRESS

 
Interoperability Event 11 & 25 June

15%

IN PROGRESS

 
Webinar on eDelivery value proposition (Member States) 26 September

0%

NOT STARTED

 
How-to video on Domibus new features 24 October

 

 

0%

NOT STARTED

 
eDelivery Interoperability Forum 24 October

 

 

0%

NOT STARTED

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

NOT STARTED

 
Dynamic Discovery Webinar 12 December

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 7 (March 2024)

100%

COMPLETED

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

NOT STARTED

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

NOT STARTED

 

Overall Project Progress

Technical

  • eDelivery 2.0 profiles (2023 drafts):
    • The disposition of public review comments following the consultation on the first drafts (2023) published: AS4 | SMP.
  • eDelivery 2.0 profiles (2024 drafts):
    • Second drafts of the eDelivery profiles published: AS4 | SMP | BDXL | ebCore Party Id.
    • 2nd public consultation (on the 2024 drafts): 8 March – 8 April. Feedback received from one person / organisation.
  • Domibus development:
    • Domibus 5.1.3 security fix release was published on .
    • Domibus 5.0.8 bug fix release published on .
    • Domibus roadmap updated: Domibus 5.2 to be released in Q4 2024, Domibus 6.0 to be released by end of 2025.
  • eDelivery Conformance Testing service:
    • Implementation of test cases for the Pull profile enhancement concluded. Deployment in production to be planned
    • Implementation of test cases for the Dynamic Sender profile enhancement ongoing
    • Analysis to strengthen the testing of the eDelivery Common Profile concluded.
    • Work also ongoing to increase the level of service maturity

Onboarding & Communication

Technical Progress

Specifications: eDelivery AS4 & SMP Profiles

Software product: Domibus

  • Domibus 5.0.8 bug fix released on the  
  • Domibus 5.1.3 bug fix released on the , containing a fix for multitenancy related issue and several library upgrades
  • Domibus 5.1.4 bug fix release, including the fixes implemented in 5.0.8, is planned for the  
  • Domibus 5.2 RC
    • Limited progress due to the effort required for several bug fix releases and the extensive maintenance and support workload. Revisited eDelivery roadmap:

      • Domibus 5.2 RC - Q4 2024 | Domibus 5.2 FR – Q4 2024

      • Domibus 6.0 RC – Q3 2025 | Domibus 6.0 FR – Q4 2025

  • Domibus new documentation framework
    • The new Domibus documentation framework and supporting processes is concluded and will be launched with the Domibus 5.0.8 release.

Software product: DomiSMP

  • DomiSMP 5.1 RC development activities are ongoing.

Software product: DomiSML

  • N/A

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

  • eDelivery AS4 1.15 profile enhancements conformance testing implementation:
    • Implementation of test cases for the Pull profile enhancement concluded. Deployment in production to be planned
    • Implementation of test cases for the Dynamic Sender profile enhancement ongoing
  • Ongoing support being provided to the SW providers testing their solutions

Software product: Docker images

  • Domibus 5.0.8 in a Tomcat + MySQL configuration Docker images for published on the (OOTS).
  • Docker image performance testing concluded

Service: PKI Service

  • N/A

Service: SML Service

  • A renewed collaboration was established with OpenPeppol. eDelivery will take part in the Peppol Critical Infrastructure Working Group and the upcoming pilot for SML federation.

Section 2: Evolutive Maintenance

Change Requests

KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
EDELGOV-112Well balancing web page DOMIBUS Admin: header takes more place than the body where are messages to monitor

Request for Change

Mar 14, 2024Mar 26, 2024
Marcio SAMPAIOErnest MUTAGANDA

APPROVED

Unresolved
EDELGOV-111Domibus List Pending Messages Request Case Sensitivity

Request for Change

Feb 14, 2024Mar 26, 2024
Marcio SAMPAIOAlexandros Christofi

APPROVED

Unresolved
EDELGOV-92eDelivery growth factor by improved DNS recommendation of SML discovery

Request for Change

Dec 2, 2022Mar 26, 2024
Joze RIHTARSICGunnar Nilsson

REJECTED

No Action
EDELGOV-89Fulfill the requirements on the BDEW AS4 Profile
Request for Change
Oct 28, 2022Sep 22, 2023
Cosmin BACIUSven Uthe

UNDER REVIEW

Unresolved
EDELGOV-76Request for investigation of using multihop functionality with AS4
Request for Change
Nov 12, 2020Sep 28, 2022
Marcio SAMPAIOOle Vilstrup Møller


POSTPONED

On hold
EDELGOV-51Dynamic Service discovery - SML/SMP change request

Request for Change

Sep 28, 2018Sep 22, 2023
Marcio SAMPAIOCIF VSRS

UNDER REVIEW

Unresolved

Release Calendar

Section 3: Support Office

Incident Management

SMT - Workload Details

The volume of opened and handled SMT tickets decreased slightly in February compared to the month before, but not significantly.  The peak of requests in January and February 2023 is due to the large number of renew/issuing of PKI Certificates as the deadline to renew PKI certificates from T-Systems to CommisSign was the 31/01/2023. In February 2024, there were a lot of questions from users on Domibus migration, the FS plugin usage, Docker versions available for Domibus, AS4 connectivity test requests, etc.

Email Interaction

For eDelivery, received mails were related to:

  • Requests for AS4 connectivity test with SHAOKE (Chinese logistics company), Everysite
  • eDelivery conformance tests: ongoing tests on new platform for OpenTunnel, OpenText and Harmony successfully passed the tests (OpenText on the ‘old’ platform, Harmony on the ‘new’ GITB) and their solution was published on the AS4 conformant solution page on Digital website.
  • Answers for the “Public Consultations on eDelivery AS4 profile 2.0 and eDelivery SMP profile 2.0”
  • Questions from users: Domibus (Domibus 5.1.1 upgrade issues with JMS plugin, Domibus 5.1.2 and active MQ Broker, WS plugin behaviour, Docker questions, Domibus 5.1.2 and case sensitivity in ListPendingMessages, Domibus migration to 5.0.6 (EUCEG), certificate and elliptic curve, multitenancy and FS plugin), SML/SMP (SMP/SMK certificate update/renewal), PKI certificates (UDB, EUCEG, DECIDE, CixP, PCN), TAPAS (ICS2 connectivity test assistance requests (re-directed to the National service desks), onboarding request forwarded to National Helpdesk), followup of issues raised to Oracle support)
  • There was a total of 744 emails in the FMB. We have removed 59 emails for SML Inconsistency, 16 alerts, 120 xmatters and 9 emails from PKI CommisSign from the count, which makes a total of 540 received mails for the reporting month.

PKI

In February 2024, 5 certificates were issued: 1 ECDB, 1 PCN, 2 DECIDE (European Council), 1 UDB.

Operations Management

SML – Availability

The achieved availability for SML1 was within the target for the month of February.


  • No labels