OVERALL STATUS: YELLOW
Date:
Reporting Period: toProject Owner (PO): DG CNECT
Business Manager (BM): Maya Madrid
Solution Provider (SP): DIGIT
Project Manager (PM): Bogdan Dumitriu
Section 1: Project Management
Milestones Progress
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments |
---|---|---|---|---|---|
Domibus 5.0.6 | 100% | COMPLETED | |||
Domibus 5.1.1 | 81% | IN PROGRESS | |||
Domibus 5.2 RC | 67% | IN PROGRESS | Release date postponed from the , following the roadmap review | ||
Domibus 5.2 FR | 0% | NOT STARTED | Release date postponed from the , following the roadmap review | ||
Domibus - technical consolidation / internal tasks | 0% | NOT STARTED | |||
Domibus 6.0 RC | Q4 2024 | 0% | NOT STARTED | ||
Domibus 6.0 FR | Q1 2025 | Q1 2025 | 0% | NOT STARTED | |
DomiSML 4.2.1 | 100% | COMPLETED | Bug fix release mainly focused on the upgrade of 3rd party libraries | ||
DomiSML 4.3 RC | 95% | IN PROGRESS | Anticipated form the | ||
DomiSML 4.3 FR | 0% | NOT STARTED | Anticipated form the | ||
DomiSML 5.0 RC | 0% | NOT STARTED | |||
DomiSML 5.0 FR | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward | ||
DomiSMP 5.1 RC | 0% | NOT STARTED | |||
DomiSMP 5.1 FR | 0% | NOT STARTED | |||
eDelivery AS4 2.0 profile | 80% | IN PROGRESS | The main focus of this profile version is the upgrade to new cryptographic algorithms. Public consultation started in June. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. | ||
eDelivery SMP 2.0 profile | 80% | IN PROGRESS | The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0. Public consultation started in June. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. | ||
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 12% | IN PROGRESS | |||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 4% | IN PROGRESS | |||
Migration to GITLab | Q4 2024 | 12% | ON HOLD | The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024. | |
Define and implement a new documentation model for the eDelivery sample implementations | 45% | IN PROGRESS | Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer. A new date will be indicated following the re-planning. | ||
Newsroom account for eDelivery (for mailing list management) | 4% | IN PROGRESS | Milestone will be considered completed when we have a newsroom with at least 1 newsletter approved by PO. The eDelivery newsletter for June has been successfully circulated via newsroom. | ||
Update eDelivery projects & stakeholders repository | 15% | IN PROGRESS | The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers. | ||
Overhaul of eDelivery communication materials | 25% | IN PROGRESS | This includes the eDelivery tutorial, flyers, leaflet, PPT presentation materials. | ||
Increase average online engagement rate to 15% | 60% | IN PROGRESS | The current average engagement rate on Twitter is 7-8%. | ||
Increase the number of newsletter subscribers to 1100 | 100% | IN PROGRESS | The number of Newsletter subscribers for the June Newsletter was at 1281 | ||
20% | IN PROGRESS | Preliminary deck of slides, approached external speakers | |||
Ninth meeting of the Informal Cooperation Network for eDelivery (ICN) | 30% | IN PROGRESS | AGM issues have been solved. Additional email has been sent. | ||
eDelivery Interoperability Forum 28 November 2023 | 15% | IN PROGRESS | Preliminary Agenda includes presentation from one eDelivery project, changes to the presentation of suppliers and conformance testing. |
Overall Project Progress
Technical
- Public consultation of eDelivery AS4 2.0 and SMP 2.0 profiles open, set to end on . No feedback received so far. It will be advertised/highlighted again in the next issue of our newsletter.
- Sustained efforts to improve the high-end performance of Domibus 5.0. Most of the improvements were released as part of Domibus 5.0.6 on , with some additional ones being prepared for Domibus 5.0.7. The entire set will also be released for the Domibus 5.1 product line, as part of Domibus 5.1.1 on .
- Domibus 5.2 development activities ongoing, with the release planned for following the review of the eDelivery roadmap.
- DomiSML 4.1.1 maintenance release was published on and the DomiSML 4.3 RC feature released is ready and will be released on .
- With the migration to the new conformance testing platform complete, work was initiated to:
- strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products)
- extend the tests to allow software vendors and service providers to test their products/services also against all the optional parts of the eDelivery AS4 1.15 profile, as currently only 2 (of 6) such optional profile parts are testable.
Onboarding & Communication
- eDelivery newsletter no. 5 will be sent in mid-September.
- Several events are planned for the autumn (webinar on eDelivery value proposition, eDelivery Informal Cooperation Network hybrid meeting and eDelivery Interoperability Forum meeting)
Technical Progress
Specifications: eDelivery AS4 Profile
- Public consultation of eDelivery AS4 2.0 and SMP 2.0 profiles open, set to end on . No feedback received so far. It will be advertised/highlighted again in the next issue of our newsletter.
Software product: Domibus
- Domibus 5.0.6 bug fix release took place on the .
- Works on a Domibus 5.0.7 bug fix release initiated, release date yet to be defined.
- Domibus 5.1.1 bug fix release being developed, release date planned for the . It has approximately the same scope as Domibus 5.0.6.
- Domibus 5.2 RC development activities ongoing, release planned for the following the eDelivery roadmap review.
- Latest iteration of the eDelivery roadmap concluded, please find the updated release dates:
- Domibus 5.2 FR -
- Domibus 6.0 RC - Q4 2024*
- Domibus 6.0 FR - Q1 2025*
* Concrete dates not defined due to dependencies with a 3rd party library roadmap and potential budgetary constrains.
Software product: DomiSMP
- DomiSMP 5.1 RC development activities to be initiated on the , release date planned for the .
- DomiSMP 5.1 FR planned for the .
Software product: DomiSML
- DomiSML 4.2.1 bug fix release, mainly focused on 3rd party libraries upgrade, was released on the .
- DomiSML 4.3 RC development activities concluded, release is will take place on the .
- Latest iteration from the eDelivery roadmap concluded, please find the updated release
- DomiSML 5.0 RC - **
- DomiSML 5.0 FR - **
- DomiSML 4.2.1 bug fix release, mainly focused on 3rd party libraries upgrade, was released on the .
** Tentative dates dependent on budget confirmation as of May 2025 onward.
Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service
- With the migration to the new platform complete, work was initiated to extend the tests encoded in the platform in order to allow software vendors and service providers to test their products' and/or services' implementation of all of the eDelivery AS4 1.15 profile enhancements (which are optional parts of the eDelivery specifications). Currently only 2 (of 6) such profile enhancements are testable.
- Analysis is also underway to strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products), since the current level of testing is unequal (some parts are overtested while some others are under- or even un-tested). This will be given priority over the completion of the previous point.
- In parallel, minor improvements are being added to the platform and to the existing test cases.
- With the migration to the new platform complete, work was initiated to extend the tests encoded in the platform in order to allow software vendors and service providers to test their products' and/or services' implementation of all of the eDelivery AS4 1.15 profile enhancements (which are optional parts of the eDelivery specifications). Currently only 2 (of 6) such profile enhancements are testable.
Software product: Docker images
- Docker images for Domibus 5.1.x in a Tomcat + MySQL configuration – production readiness activities ongoing. Stress and performance tests being executed. This is an OOTS requirement.
- Docker images for Domibus 5.1.x in a Tomcat + MySQL configuration – production readiness activities ongoing. Stress and performance tests being executed. This is an OOTS requirement.
Service: PKI Service
- N/A
Service: SML Service
- N/A
Section 2: Evolutive Maintenance
Change Requests
Release Calendar
Section 3: Support Office
Incident Management:
SMT - workload details:
The number of handled SMT tickets decreased in July 2023, while the number of opened SMT tickets remained stable during the last 4 months. Requests from users concern questions on Domibus and the different plugins, Domibus migration, AS4 connectivity test issues, etc.
Email interaction:
For eDelivery, received mails were related to:
- Requests for AS4 connectivity test with Huzar software, State Institute for Drug Control (Štátny ústav pre kontrolu liečiv) SUKL
- Questions from users: Domibus (Domibus with Tomcat on Docker, JMS plugin, FS plugin and JDB connection, messages not displayed in Admin console, question on TLS certificates), SML/SMP (SMP/SMK certificate update/renewal, service group creation, participants registration on SML), PKI certificates ( ECDB and UDB), questions on the PKI eDelivery service, TAPAS (Oracle RCA and recommendations for CCNEB to follow, issue to save configuration changes in admin console, AS4 connection issue with Air France KLM, questions on eArchiving)
- There was a total of 494 emails in the FMB. We have removed 60 emails for SML Inconsistency and 7 emails from PKI CommisSign from the count, which makes a total of 324 received mails for the reporting month.
PKI:
In July 2023, 3 certificates were issued: 1 EUDAMED and 2 ECDB and 1 EPREL certificate was rejected.
Operations management:
SML – Availability:
The achieved availability for SML service was 100% for the month of July 2023 (the target is 99.80%).