OVERALL STATUS:Select one of the following status:
Date:
Reporting Period: to
Project Owner (PO):DG CNECT
Business Manager (BM): Maya Madrid
Solution Provider (SP): DIGIT
Project Manager (PM): Bogdan Dumitriu
Section 1: Project Management
Milestones Progress
Describe the progress made on the respective milestones throughout the reporting period. In case you wish to include information on future activities (next steps), please use the dedicated column and clearly separate tasks you have worked on throughout the reporting period from those you will work on in the future.
The main focus of this profile version is the upgrade to new cryptographic algorithms.
Public consultation started in June.
Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.
eDelivery SMP 2.0 profile
80%
The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.
Public consultation started in June.
Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.
Conformance testing service: Full support for eDelivery AS4 1.15 profile
12%
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile
4%
Migration to GITLab
Q4 2024
12%
The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations
45%
Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer. A new date will be indicated following the re-planning.
Newsroom account for eDelivery (for mailing list management)
4%
Milestone will be considered completed when we have a newsroom with at least 1 newsletter approved by PO. The eDelivery newsletter for June has been successfully circulated via newsroom.
AGM issues have been solved. Additional email has been sent.
eDelivery Interoperability Forum 28 November 2023
15%
Preliminary Agenda includes presentation from one eDelivery project, changes to the presentation of suppliers and conformance testing.
Overall Project Progress
Technical
Public consultation of eDelivery AS4 2.0 and SMP 2.0 profiles open, set to end on . No feedback received so far. It will be advertised/highlighted again in the next issue of our newsletter.
Sustained efforts to improve the high-end performance of Domibus 5.0. Most of the improvements were released as part of Domibus 5.0.6 on , with some additional ones being prepared for Domibus 5.0.7. The entire set will also be released for the Domibus 5.1 product line, as part of Domibus 5.1.1 on .
Domibus 5.2 development activities ongoing, with the release planned for following the review of the eDelivery roadmap.
DomiSML 4.1.1 maintenance release was published on and the DomiSML 4.3 RC feature released is ready and will be released on .
With the migration to the new conformance testing platform complete, work was initiated to:
strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products)
extend the tests to allow software vendors and service providers to test their products/services also against all the optional parts of the eDelivery AS4 1.15 profile, as currently only 2 (of 6) such optional profile parts are testable.
Onboarding & Communication
eDelivery newsletter no. 5 will be sent in mid-September.
Several events are planned for the autumn (webinar on eDelivery value proposition, eDelivery Informal Cooperation Network hybrid meeting and eDelivery Interoperability Forum meeting)
Technical Progress
Specifications: eDelivery AS4 Profile
Public consultation of eDelivery AS4 2.0 and SMP 2.0 profiles open, set to end on . No feedback received so far. It will be advertised/highlighted again in the next issue of our newsletter.
Software product: Domibus
Domibus 5.0.6 bug fix release took place on the .
Works on a Domibus 5.0.7 bug fix release initiated, release date yet to be defined.
Domibus 5.1.1 bug fix release being developed, release date planned for the . It has approximately the same scope as Domibus 5.0.6.
Domibus 5.2 RC development activities ongoing, release planned for the following the eDelivery roadmap review.
Latest iteration of the eDelivery roadmap concluded, please find the updated release dates:
Domibus 5.2 FR -
Domibus 6.0 RC - Q4 2024*
Domibus 6.0 FR - Q1 2025*
* Concrete dates not defined due to dependencies with a 3rd party library roadmap and potential budgetary constrains.
Software product:DomiSMP
DomiSMP 5.1 RC development activities to be initiated on the , release date planned for the .
DomiSMP 5.1 FR planned for the .
Software product: DomiSML
DomiSML 4.2.1 bug fix release, mainly focused on 3rd party libraries upgrade, was released on the .
DomiSML 4.3 RC development activities concluded, release is will take place on the .
Latest iteration from the eDelivery roadmap concluded, please find the updated release
DomiSML 5.0 RC - **
DomiSML 5.0 FR - **
** Tentative dates dependent on budget confirmation as of May 2025 onward.
With the migration to the new platform complete, work was initiated to extend the tests encoded in the platform in order to allow software vendors and service providers to test their products' and/or services' implementation of all of the eDelivery AS4 1.15 profile enhancements (which are optional parts of the eDelivery specifications). Currently only 2 (of 6) such profile enhancements are testable.
Analysis is also underway to strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products), since the current level of testing is unequal (some parts are overtested while some others are under- or even un-tested). This will be given priority over the completion of the previous point.
In parallel, minor improvements are being added to the platform and to the existing test cases.
Software product: Docker images
Docker images for Domibus 5.1.x in a Tomcat + MySQL configuration – production readiness activities ongoing. Stress and performance tests being executed. This is an OOTS requirement.
Service: PKI Service
N/A
Service: SML Service
N/A
Section 2: Evolutive Maintenance
Change Requests
Release Calendar
Section 3: Support Office
Incident Management:
SMT - workload details:
The number of handled SMT tickets decreased in July 2023, while the number of opened SMT tickets remained stable during the last 4 months. Requests from users concern questions on Domibus and the different plugins, Domibus migration, AS4 connectivity test issues, etc.
Email interaction:
For eDelivery, received mails were related to:
Requests for AS4 connectivity test with Huzar software, State Institute for Drug Control (Štátny ústav pre kontrolu liečiv) SUKL
Questions from users: Domibus (Domibus with Tomcat on Docker, JMS plugin, FS plugin and JDB connection, messages not displayed in Admin console, question on TLS certificates), SML/SMP (SMP/SMK certificate update/renewal, service group creation, participants registration on SML), PKI certificates ( ECDB and UDB), questions on the PKI eDelivery service, TAPAS (Oracle RCA and recommendations for CCNEB to follow, issue to save configuration changes in admin console, AS4 connection issue with Air France KLM, questions on eArchiving)
There was a total of 494 emails in the FMB. We have removed 60 emails for SML Inconsistency and 7 emails from PKI CommisSign from the count, which makes a total of 324 received mails for the reporting month.
PKI:
In July 2023, 3 certificates were issued: 1 EUDAMED and 2 ECDB and 1 EPREL certificate was rejected.
Operations management:
SML – Availability:
The achieved availability for SML service was 100% for the month of July 2023 (the target is 99.80%).