Project progress
DOMIBUS:
- The release 4.2.2 (minor bugs and OWASP detected vulnerabilities fix) took place on the
- Version 4.1.8 (CXF library upgrade, and several security fixes) was released on the
- 5.0 RC continue to progress, now at a good pace. Release date projected for Q1 2022, however the uncertainty in terms of future budget remains, making the service disruption risk due to potential lack of budget availability still present.
- BD asked MM opinion regarding the news on the release of Domibus 5.0. MM said that this should be communicated only when there will be clarity on the funds for eDelivery. BD informed that this delay is jeopardising reputation of the building block. An option could be to announce a tentative date and inform that final date is dependent on DEP WP approval. BD informed that backwards compatibility would be broken with eDelivery plugins in Domibus 5.0, meaning that stakeholders would need to plan in advance their upgrade. Also, some users of version 4.1.x would need to rely on the published roadmap in order to plan the upgrade to v5.0, given that v4.1.x would stop being supported at the end of June 2021. BD noted that v4.2.x would still be supported into 2022.
SML:
- SMP 4.2 RC (Use EU Login for SMP console | Upgrade libraries to latest possible versions and fix OWASP threats | Security features and updates) on hold due to the need to focus on other activities during the first half of 2021.
SMP:
- No planned activities
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.1.3 | 29/Nov/19 | 10/Feb/20 | 100% | COMPLETED | CXF upgrade (plugin and security issue) |
Domibus 4.1.6 | 11/Nov/20 | 26/Nov/20 | 100% | COMPLETED | Libraries update following security vulnerabilities reported |
Domibus 4.1.7 | 13/Jan/21 | 17/Feb/21 | 100% | COMPLETED | Postponed from the 12th to the 17th Feb | Upgrade specific libraries to lasts possible versions to address OWASP detected threats | fix double decompressing of payloads issue |
Domibus 4.1.8 | 10/Mar/21 | 22/Jun/21 | 100% | COMPLETED | bug fix release | CXF library upgrade Release currently on hold due to a dependency with a upcoming release of a 3rd party library |
12/Nov/19 | 21/Sep/20 | 100% | COMPLETED | ||
Domibus 4.2 FR | 22/Sep/20 | 17/Dec/20 | 100% | COMPLETED | released on the 17th Dec, instead of the planned date of the 10th, due to a last minute detection of a bug |
Domibus 4.2.1 | 15/Jan/21 | 23/Mar/21 | 100% | COMPLETED | Postponed from the 29th Jan | Bug fix release -UUM&DS caching issue | Deletion policy extension fix | CXF library upgrade |
Domibus 4.2.2 | 25/Mar/21 | 26/May/21 | 100% | COMPLETED | Bug fix release | OWASP detected threats |
14/Sep/20 | Q1 2022 | 55% | ONGOING | Release to be postponed from 17/Sep/21 to a new date yet to be determined | |
Domibus 5.0 FR | 04/Oct/21 | Q1 2022 | - | NOT STARTED | Release to be postponed from 17/Dec/21 to a new date yet to be determined |
SML 4.0.2 | 29/Nov/19 | 18/Feb/20 | 100% | COMPLETED | code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way. |
SML 4.1 Acceptance | 12/Oct/20 | 18/Jan/21 | 100% | COMPLETED | Postponed from 10/Nov/20 to 18Jan/21 due to an important security enhancement that became possible due to a policy change at SNET level. Security features and updates | Upgrade libraries to latest possible versions and fix OWASP threats |
SML 4.1 Production release | 20/Jan/21 | 16/Feb/21 | 100% | COMPLETED | |
01/Nov/21 | 01/Jun/21 | - | ON HOLD | Use EU Login for SMP console | Upgrade libraries to lastest possible versions and fix OWASP threats | Security features and updates | |
SMP 4.2 FR | 01/Jun/21 | 01/Jul/21 | - | ON HOLD | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 100% | COMPLETED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 8/Jun/2020 | 100% | COMPLETED | Release date: 8th June Release delayed from the 31st March to the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
Operations
Incident Management:
Operations management: