703039867OVERALL STATUS: YELLOW
Date:
Reporting Period: toProject Owner (PO): DG CNECT
Business Manager (BM): Maya Madrid
Solution Provider (SP): DIGIT
Project Manager (PM): Bogdan Dumitriu
Section 1: Project Management
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments |
---|---|---|---|---|---|
Domibus 5.1.8 |
|
| 85% | IN PROGRESS | |
Domibus 5.2 RC | Q4 2025 | 80% | IN PROGRESS | ||
Domibus 5.2 FR | Q4 2025 | Q4 2025 | 0% | NOT STARTED | |
Domibus - technical consolidation / internal tasks | Q4 2025 | Q1 2026 | 0% | NOT STARTED | |
Domibus 6.0 RC | Q1 2026 | Q2 2026 | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward |
Q3 2026 | Q4 2026 | 0% | NOT STARTED | ||
DomiSML 5.0 RC | 90% | IN PROGRESS | |||
DomiSML 5.0 FR | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward | ||
DomiSML 5.0.1 |
|
| 0% | NOT STARTED | |
DomiSMP 5.1.1 |
|
| 0% | NOT STARTED | |
DomiSMP 5.2 RC |
|
| 0% | NOT STARTED | |
DomiSMP 5.2 FR |
|
| 0% | NOT STARTED | |
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 65% | IN PROGRESS | Support for pull enhancement, dynamic sender and dynamic receiver profile enhancements to be introduced in June 2025, but support for Split & Join (the last unsupported profile enhancement) postponed to late 2025. | ||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 52% | ON HOLD | |||
Migration to GITLab | end 2027 | 12% | ON HOLD | The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q4 2025 as use of Atlassian tools (JIRA, BitBucket, Bamboo) currently is extended until February 2026. | |
Update of eDelivery reusing projects & stakeholders repository | | 30% | IN PROGRESS | The milestone will be considered completed when all the eDelivery reusing projects pages are updated and confirmed in Jira with the corresponding project managers. | |
eDelivery Self-Assessment |
|
| 95% | IN PROGRESS | Review and update to the relating documents to be available on the eDelivery website. |
Pitch and launch joint Building Blocks social media account | 70% | IN PROGRESS | Launch social media accounts together with other Building Blocks. | ||
Webinar on eDelivery value proposition (Member States) on 3 April |
| 100% | COMPLETED | Presentations and recordings published. All event follow-up activities closed. | |
How-to video on Domibus new features 2024 Q4 |
|
| 0% | NOT STARTED | |
Trust Models Webinar on 19 June |
|
| 50% | IN PROGRESS | |
12th eDelivery Informal Cooperation Network meeting 7 May 2025 |
|
| 90% | IN PROGRESS | The slides have been published. Recordings, meeting minutes and post-event article to be published. |
eDelivery Newsletter No. 11 (March 2025) |
|
| 100% | COMPLETED | The newsletter No. 11 has been issued on for 1584 recipients. Due to external circumstances the newsletter could not be sent via Newsroom earlier. |
Digital Building Blocks Newsletter No. 7 (May 2025) |
|
| 20% | IN PROGRESS | The content has been identified and is currently in progress to be prepared. |
New conformance testing reports design |
|
| 99% | IN PROGRESS | |
Content review of the website “get started” section |
|
| 30% | IN PROGRESS | |
Cost estimation tool |
|
| 75% | IN PROGRESS | |
eDelivery tutorial |
|
| 30% | IN PROGRESS | |
eDelivery Interoperability Event on 16 September 2025 |
|
| 5% | IN PROGRESS | Ongoing preparation. |
eDelivery Interoperability Forum Meeting on 16 October 2025 |
|
| 5% | IN PROGRESS | Ongoing preparation. |
eDelivery Newsletter No. 12 (May-June 2025) |
|
| 15% | IN PROGRESS | The content has been identified and is currently in progress to be prepared. |
*All milestones presented in the table above are subject to confirmation or re-evaluation once the new MoU between DIGIT and DG CNECT is signed.
Technical Progress
Specifications: eDelivery AS4, SMP, BDXL, ebCore Party Id Profiles
- In follow-up with ENISA, change request for the inclusion of EdDSA in the (formerly SOG-IS, currently ECCG) Agreed Cryptographic Mechanisms document will be prepared and submitted by DIGIT.
- This will require a new collaboration with the cryptography professor that supported the preparation of the eDelivery AS4 2.0 specifications in 2022.
- Following the remark during the Interoperability Forum concerning the incorrect use of Two-Way MEP in Domibus and the incorrect validation thereof in the conformance testing platform, a technical analysis took place and both the conformance testing platform and Domibus will be updated by the end of the year to address the issue.
Software product: Domibus
- The release of Domibus 5.1.8, which includes improvements to the pull mechanism and other bug fixes, had to be postponed due to the required upgrade to DSS library version 5.13.1. This upgrade is necessary to support TLv6 by June this year. As well as the need to analysis 3rd party reported vulnerabilities. The release is now planned for .
- Domibus 5.2 RC development work is ongoing, again with the progress severely hampered during the reporting period due to effort required to maintain the currently supported Domibus product lines (5.0.X and 5.1.X) along with the documented capacity constraints it has been decided to further postponed the Domibus 5.2 RC to Q4 2025 and FR to Q4 2025.
Software product: DomiSMP
- DomiSMP 5.1.1 release planned for the .
- DomiSMP 5.2 RC development work to be initiated on the .
Software product: DomiSML
- DomiSML 5.0 RC was released on the and the FR on the .
Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service
- eDelivery AS4 1.15 profile enhancements conformance testing implementation:
- Implementation of test cases for the Dynamic Receiver profile enhancement concluded
- Release of version 2025.06 of the platform is planned for the end of June, including in the scope:
- Support for Dynamic discovery testing
- Support Pull Profile testing
- Several bug fixes
- The standalone tool that will provide limited self-testing/self-validation support to solution providers preparing 2.0-conformant solutions (eDelivery2 AS4 Security Validator) is ready and will be published by the end of May.
Software product: Docker images
- N/A
Service: PKI Service
- N/A
Service: SML Service
- SML Service is being migrated from WebLogic to Tomcat in the data centre. The acceptance environment has already been successfully migrated, the production one will follow.
Section 2: Evolutive Maintenance
Change Requests
Key | Summary | T | Created | Updated | Status | Resolution |
---|---|---|---|---|---|---|
EDELGOV-134 | Case Sensitivity of partyIdType and partyId in Domibus pMode | Mar 26, 2025 15:48 | May 20, 2025 15:57 | UNDER REVIEW | Unresolved | |
EDELGOV-133 | Support official Docker images | Mar 26, 2025 15:21 | May 20, 2025 17:12 | UNDER REVIEW | Unresolved | |
EDELGOV-89 | Fulfill the requirements on the BDEW AS4 Profile | Oct 28, 2022 17:03 | Feb 11, 2025 17:33 | UNDER REVIEW | Unresolved | |
EDELGOV-76 | Request for investigation of using multihop functionality with AS4 | Nov 12, 2020 17:51 | Sept 28, 2022 07:56 | POSTPONED | On hold | |
EDELGOV-51 | Dynamic Service discovery - SML/SMP change request | Sept 28, 2018 15:04 | Feb 11, 2025 16:35 | UNDER REVIEW | Unresolved |
Release Calendar
Section 3: Support Office
Incident Management
SMT - workload details
The number of handled, opened and resolved SNOW tickets is slightly decreasing since February 2025 after a significant increase in July 2024 and the months after. This can be explained by the fact that there are less request to renew expired eDelivery PKI Certificates as they are progressively being renewed. Questions from users are questions on Docker, Domibus migration (database migration issues and others), plugins, conformance and connectivity tests requests and questions, questions on Domibus/DomiSMP etc. JIRA internal tasks concern SML and Domibus releases, new TomCat cluster environment for SML 5.0 in CIPA E-DELIVERY, some maintenance tasks on the infrastructure (Ubuntu and Rundeck updates, Dedicated data disk set up in TESOPROD01 for the Connectivity Testing Domibus and SMP), etc.
Email interaction
In March 2025, received mails were related to:
- eDelivery AS4 connectivity test: Tigron, Euro Information, BEO, Appfuxion Consulting Sdn. Bhd, Samer & Co. Shipping, TARDEK OÜ company
- eDelivery conformance tests: Opentunnel resumed conformance tests after patch 2 release, IPWorks EDI (testing of ENTSOG and additional profile enhancements), Holodeck B2B version 7.0.0 testing including new ENTSOG feature, new version of Harmony, Axway 1.15, Eufex Deutschland GmbH request for AS4 conformance test resumed conformance testing with patch 2 release (product is eConnect Europe)
- Sending of Peppol updated list of participants twice a month
- Questions from users: interest of UAE in eDelivery and Domibus, Domibus (Domibus 5.2 release date, Domibus versions using the version 2.0 of eDelivery AS4 profile, MySQL and Domibus, Java 21 support with Domibus, Domibus and multitenancy, etc.), SML/SMP (SMP/SMK certificate update/renewal, participant registration), PKI certificates (UDB, CiXP, EPREL, PCN, BRIS, EUDAMED, DECIDE), TAPAS (ICS2 connectivity test assistance requests, issue with stuck threads on DSS, error on Connection Monitoring page after PMode Update, etc.)
- There was a total of 664 emails in the FMB. We have removed 82 emails for SML Inconsistency, 20 alerts, and 28 emails from PKI CommisSign from the count, which makes a total of 534 received mails for the reporting month .
In April 2025, received mails were related to:
- eDelivery AS4 connectivity test: Tigron, Euro Information, BEO, Appfuxion Consulting Sdn. Bhd, Samer & Co. Shipping
- eDelivery conformance tests: Opentunnel resumed conformance tests after patch 2 release, IPWorks EDI (testing of ENTSOG and additional profile enhancements), Holodeck B2B version 7.0.0 testing including new ENTSOG feature, new version of Harmony, Axway 1.15, Eufex Deutschland GmbH request for AS4 conformance test resumed conformance testing with patch 2 release (product is eConnect Europe)
- Sending of Peppol updated list of participants twice a month
- Questions from users: request for the cost-estimation tool, Domibus (Domibus 5.2 release date, Domibus and Tomcat CVE-2025-24813 vulnerability, Docker, Domibus preferred architectural design, message retention period, TLS on WS plugin, etc.), SML/SMP (SMP/SMK certificate update/renewal, participant registration), PKI certificates (UDB, CiXP, IRI, EPREL, PCN, BRIS, EUDAMED, ECDB), TAPAS (ICS2 connectivity test assistance requests, request to have a sample payload of a "Validation Response" sent by CESOP to Member States, etc.)
- There was a total of 562 emails in the FMB. We have removed 60 emails for SML Inconsistency, 12 alerts, and 37 emails from PKI CommisSign from the count, which makes a total of 453 received mails for the reporting month.
PKI
In March 2025, 12 PKI certificates were issued: 2 IRI, 1 BRIS, 3 CiXP, 1 EPREL, 1 PCN, 2 ECDB, 2 EUDAMED. One UDB certificate request was rejected (not yet onboarded).
In April 2025, 16 PKI certificates were issued: 1 REPLIES, 3 CiXP, 5 EUDAMED and 7 EPREL.
Operations Management
SML – availability
The report is published on the Website of SML Service, in the last section: Link