Project progress
DOMIBUS:.
- Version 4.1 FR (Support of Large files - Split and Join | Interface with UUM&DS and STI | EU Login support | ...) was postponed from the 15th to the 31st July . This is due to a reported vulnerability in one of the libraries used in Domibus, detected in our regular OWASP dependencies check, so that the fix could be included in this release. Moreover, we are taking the opportunity to include a fix related with the ActiveMQ setup in a tomcat cluster, a bug that is critical for the CIxP Project, a project of the European Council, that will go live in September.
SMP:
- bugfix release 4.1.1 ongoing (SMP authentication improvement with CRL and CA | Improve handling shared keystore in Cluster environment | Bug fixing) to address them.
SML:
- SML 4.0 Production release deployed in the production environment and published on the CEF Portal on the as planned
eTrustEx adapter replacement Access Point plugin:
- DECIDE-Sep-Core project successfully migrated to eDelivery Access point - eTrustEx Backend Plugin in PROD, replacing the eTrustEx adapter on the
- Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) initiated. Release date yet to be defined. The focus will be directed at the migration process of the entities using the eTrustEx adapter instance.
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 70% | DELAYED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 11/Nov/19 | - | NOT STARTED | |
12/Nov/19 | 21/Sep/20 | - | NOT STARTED | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 52% | ONGOING | Bug fix release |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | TBD | - | ONGOING | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | TBD | TBD | - | NOT STARTED |