OVERALL STATUS: Status colour Yellow title yellow
Date:28 Jun
Multiexcerpt | ||
---|---|---|
| ||
Reporting Period: to |
...
Milestones Progress
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Domibus 5.0.7 |
| TBD | 63% |
| |||||||||
Domibus 5.1.1 | 78% |
| Release date postponed from the | ||||||||||
Domibus 5.2 RC | 69% |
| Release date postponed from the , following the roadmap review | ||||||||||
Domibus 5.2 FR | 0% |
| Release date postponed from the , following the roadmap review | ||||||||||
Domibus - technical consolidation / internal tasks | 0% |
| |||||||||||
Domibus 6.0 RC | Q4 2024 | 0% |
| ||||||||||
Domibus 6.0 FR | Q1 2025 | Q1 2025 | 0% |
| |||||||||
DomiSML 4.3 RC | 100% |
| Anticipated form the | ||||||||||
DomiSML 4.3 FR | 80% |
| Anticipated form the | ||||||||||
DomiSML 5.0 RC | 0% |
| |||||||||||
DomiSML 5.0 FR | 0% |
| Dependent on budget confirmation as of May 2025 onward | ||||||||||
DomiSMP 5.1 RC | 0% |
| |||||||||||
DomiSMP 5.1 FR | 0% |
| |||||||||||
eDelivery AS4 2.0 profile | 80% |
| The main focus of this profile version is the upgrade to new cryptographic algorithms. Public consultation started in June. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. | ||||||||||
eDelivery SMP 2.0 profile | 80% |
| The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0. Public consultation started in June. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. | ||||||||||
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 17% |
| |||||||||||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 15% |
| |||||||||||
Migration to GITLab | Q4 2024 | 12% |
| The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024. | |||||||||
Define and implement a new documentation model for the eDelivery sample implementations | 45% |
| Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer. A new date will be indicated following the re-planning. | ||||||||||
Newsroom account for eDelivery (for mailing list management) | ? | 10% |
| Milestone will be considered completed when we have a newsroom with at least 1 newsletter approved by PO. | |||||||||
Update eDelivery projects & stakeholders repository | 15% |
| The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers. | ||||||||||
Overhaul of eDelivery communication materials | 25% |
| This includes the eDelivery tutorial, flyers, leaflet, PPT presentation materials. | ||||||||||
Increase average online engagement rate to 15% | 30% |
| The current average engagement rate on Twitter is 5%. A change in the algorithm leads to a declining engagement rate as it favours payed-for accounts. | ||||||||||
Increase the number of newsletter subscribers to 1100 | 100% |
| The number of Newsletter subscribers for the June Newsletter was at 1281 | ||||||||||
80% |
| Final preparations are ongoing while the webinar is ready to be held. | |||||||||||
Ninth meeting of the Informal Cooperation Network for eDelivery (ICN) | 30% |
| AGM issues in process of being solved. Communication with stakeholders. | ||||||||||
eDelivery Interoperability Forum 28 November 2023 | 15% |
| Preliminary Agenda includes presentation from one eDelivery project, changes to the presentation of suppliers and conformance testing. |
Overall Project Progress
Multiexcerpt | ||
---|---|---|
| ||
Technical
Miscellaneous
Onboarding & Communication
|
...
- eDelivery AS4 1.15 profile enhancements conformance testing implementation - limited progress due to holiday of the resource responsible for this platform related activities.
- Analysis to strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products) is ongoing.
- eDelivery AS4 1.15 profile enhancements conformance testing implementation - limited progress due to holiday of the resource responsible for this platform related activities.
...
Section 2: Evolutive Maintenance
Change Requests
Jira | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Release Calendar
Section 3: Support Office
Incident Management:
SMT - workload details:
The number of handled SMT tickets increased in August 2023 compared to the previous month, while the number of opened SMT tickets remained stable during the last 4 months. Requests from are questions on Domibus and the different plugins, Domibus migration and migration scripts, AS4 connectivity test issues, etc.
Email interaction:
For eDelivery, received mails were related to:
- Requests for AS4 connectivity test with Skyport
- Conformance test request for RIM Reporting Interface Module (RIM) V2 with new GITB conformance testing platform
- Project with Poland Ministry of Digital Affairs and with EPPO: meeting organised and technical questions answered
- Questions from users: Domibus (issues with large attachments, Domibus on Docker, upgrade from 4.2.9 to 5.0, questions on WS plugin, multitenancy and plugins, issue with message stuck in WAITING_FOR_REPLY in admin console), SML/SMP (SMP/SMK certificate update/renewal, participants registration on SML), PKI certificates (EPREL, ECDB, UDB and EUDAMED), Peppol question on AS4 implementation and signing of AS4 Error messages, TAPAS (ICS2 connectivity test assistance requests (re-directed to the National service desks), AS4 connection issue with Air France KLM)
- There was a total of 580 emails in the FMB. We have removed 62 emails for SML Inconsistency and 7 emails from PKI CommisSign from the count, which makes a total of 511 received mails for the reporting month.
PKI:
In August 2023, 6 certificates were issued: 1 ECDB and 6 EPREL.
Operations management:
SML – Availability:
The achieved availability for SML service within the target for the month of August
...