Business Manager (BM): Maya MadridMadrid
Solution Provider (SP): DIGIT
...
Section 1: Project Management
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Domibus 5.1.8 |
|
| 85% |
| |||||||||
Domibus 5.2 RC | Q4 2025 | 80% |
| ||||||||||
Domibus 5.2 FR | Q4 2025 | Q4 2025 | 0% |
| |||||||||
Domibus - technical consolidation / internal tasks | Q4 2025 | Q1 2026 | 0% |
| |||||||||
Domibus 6.0 RC | Q1 2026 | Q2 2026 | 0% |
| Dependent on budget confirmation as of May 2025 onward | ||||||||
Q3 2026 | Q4 2026 | 0% |
| ||||||||||
DomiSML 5.0 RC | 90% |
| |||||||||||
DomiSML 5.0 FR | 0% |
| Dependent on budget confirmation as of May 2025 onward | ||||||||||
DomiSML 5.0.1 |
|
| 0% |
| |||||||||
DomiSMP 5.1.1 |
|
| 0% |
| |||||||||
DomiSMP 5.2 RC |
|
| 0% |
| |||||||||
DomiSMP 5.2 FR |
|
| 0% |
| |||||||||
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 65% |
| Support for pull enhancement, dynamic sender and dynamic receiver profile enhancements to be introduced in June 2025, but support for Split & Join (the last unsupported profile enhancement) postponed to late 2025. | ||||||||||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 52% |
| |||||||||||
Migration to GITLab | end 2027 | 12% |
| The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q4 2025 as use of Atlassian tools (JIRA, BitBucket, Bamboo) currently is extended until February 2026. | |||||||||
Update of eDelivery reusing projects & stakeholders repository | | 30% |
| The milestone will be considered completed when all the eDelivery reusing projects pages are updated and confirmed in Jira with the corresponding project managers. | |||||||||
eDelivery Self-Assessment |
|
| 95% |
| Review and update to the relating documents to be available on the eDelivery website. | ||||||||
Pitch and launch joint Building Blocks social media account | 70% |
| Launch social media accounts together with other Building Blocks. | ||||||||||
Webinar on eDelivery value proposition (Member States) on 3 April |
| 100% |
| Presentations and recordings published. All event follow-up activities closed. | |||||||||
How-to video on Domibus new features 2024 Q4 |
|
| 0% |
| |||||||||
Trust Models Webinar on 19 June |
|
| 50% |
| |||||||||
12th eDelivery Informal Cooperation Network meeting 7 May 2025 |
|
| 90% |
| The slides have been published. Recordings, meeting minutes and post-event article to be published. | ||||||||
eDelivery Newsletter No. 11 (March 2025) |
|
| 100% |
| The newsletter No. 11 has been issued on for 1584 recipients. Due to external circumstances the newsletter could not be sent via Newsroom earlier. | ||||||||
Digital Building Blocks Newsletter No. 7 (May 2025) |
|
| 20% |
| The content has been identified and is currently in progress to be prepared. | ||||||||
New conformance testing reports design |
|
| 99% |
| |||||||||
Content review of the website “get started” section |
|
| 30% |
|
Cost estimation tool |
|
| 75% |
|
eDelivery tutorial |
|
| 30% |
|
eDelivery |
Interoperability Event on 16 September 2025 |
|
| 5% |
| Ongoing preparation. | ||||||||
eDelivery Interoperability Forum Meeting on 16 October 2025 |
|
| 5% |
| Ongoing preparation. | ||||||||
eDelivery Newsletter No. 12 (May-June 2025) |
|
| 15% |
| The content has been identified and is currently in progress to be prepared. |
*All milestones presented in the table above are subject to confirmation or re-evaluation once the new MoU between DIGIT and DG CNECT is signed.
...
Specifications: eDelivery AS4, SMP, BDXL, ebCore Party Id Profiles
- In follow-up with ENISA, it was agreed for DIGIT to prepare and submit a change request for the inclusion of EdDSA in the (formerly SOG-IS, currently ECCG) Agreed Cryptographic Mechanisms document will be prepared and submitted by DIGIT.
- This will require a new collaboration with the cryptography professor that supported the preparation of the eDelivery AS4 2.0 specifications in 2022.
- Following the remark during the Interoperability Forum concerning the incorrect use of Two-Way MEP in Domibus and the incorrect validation thereof in the conformance testing platform, a technical analysis took place and both the conformance testing platform and Domibus will be updated by the end of the year to address the issue.
...
Service: PKI Service
- N/A
Service: SML Service
- SML Service security plan review completed. Signature blocked by ARES file for assignment of System Owner responsibility not being signed in CNECT.
- SML Service is being migrated from WebLogic to Tomcat in the data centre. The acceptance environment has already been successfully migrated, the production one will follow. Milestone reached in collaboration with OpenPeppol: they officially adopted the migration plan from CNAME to NAPTR records (cf. Peppol CNAME to NAPTR Migration Process). Once completed (tentatively we will be able to remove a half of the Peppol records from the SML Service
- .
Section 2: Evolutive Maintenance
...
Key | Summary | T | Created | Updated | Status | Resolution | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
EDELGOV-134 | Case Sensitivity of partyIdType and partyId in Domibus pMode | Mar 26, 2025 15:48 | May 20, 2025 15:57 | | Unresolved | |||||||||
EDELGOV-133 | Support official Docker images | Mar 26, 2025 15:21 | May 20, 2025 17:12 | | Unresolved | |||||||||
EDELGOV-89 | Fulfill the requirements on the BDEW AS4 Profile | Oct 28, 2022 17:03 | Feb 11, 2025 17:33 | | Unresolved | |||||||||
EDELGOV-76 | Request for investigation of using multihop functionality with AS4 | Nov 12, 2020 17:51 | Sept 28, 2022 07:56 | | On hold | |||||||||
EDELGOV-51 | Dynamic Service discovery - SML/SMP change request | Sept 28, 2018 15:04 | Feb 11, 2025 16:35 | | Unresolved |
...