703039867OVERALL STATUS: Select one of the following status:      

Date:

Reporting Period:   to  


Project Owner (PO): DG CNECT

Business Manager (BM): Maya Madrid 

Solution Provider (SP): DIGIT

Project Manager (PM): Bogdan Dumitriu

Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.1.8

 

 

85%


Domibus 5.2 RC

Q4 2025
80%


Domibus 5.2 FR
Q4 2025
Q4 2025
0%


Domibus - technical consolidation / internal tasks

Q4 2025

Q1 2026

0%


Domibus 6.0 RC

Q1 2026

Q2 2026

0%

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

Q3 2026

Q4 2026

0%


DomiSML 5.0 RC

90%


DomiSML 5.0 FR

0%

Dependent on budget confirmation as of May 2025 onward

DomiSML 5.0.1

 

 

0%


DomiSMP 5.1.1

 

 

0%


DomiSMP 5.2 RC

 

 

0%


DomiSMP 5.2 FR

 

 

0%


Conformance testing service: Full support for eDelivery AS4 1.15 profile

65%

Support for pull enhancement, dynamic sender and dynamic receiver profile enhancements to be introduced in June 2025, but support for Split & Join (the last unsupported profile enhancement) postponed to late 2025.
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile

52%


Migration to GITLab

end 202712%

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q4 2025 as use of Atlassian tools (JIRA, BitBucket, Bamboo) currently is extended until February 2026.
Update of eDelivery reusing projects & stakeholders repository

 

30%

The milestone will be considered completed when all the eDelivery reusing projects pages are updated and confirmed in Jira with the corresponding project managers.
eDelivery Self-Assessment

 

 

95%

Review and update to the relating documents to be available on the eDelivery website.
Pitch and launch joint Building Blocks social media account

70%

Launch social media accounts together with other Building Blocks. 
Webinar on eDelivery value proposition (Member States) on 3 April

 

100%

Presentations and recordings published. All event follow-up activities closed.

How-to video on Domibus new features 2024 Q4

 

  

0%


Trust Models Webinar on 19 June

 

 

50%


12th eDelivery Informal Cooperation Network meeting 7 May 2025

 

 

90%

 The slides have been published. Recordings, meeting minutes and post-event article to be published.
eDelivery Newsletter No. 11 (March 2025)

 

 

100%

The newsletter No. 11 has been issued on for 1584 recipients. Due to external circumstances the newsletter could not be sent via Newsroom earlier.

Digital Building Blocks Newsletter No. 7 (May 2025)

 

 

20%

The content has been identified and is currently in progress to be prepared.
New conformance testing reports design

 

 

99%


Content review of the website “get started” section 

 

 

30%


Cost estimation tool 

 

 

75%


eDelivery tutorial

 

 

30%


eDelivery Interoperability Event on 16 September 2025 

 

 

5%

Ongoing preparation.
eDelivery Interoperability Forum Meeting  on 16 October 2025

 

 

5%

Ongoing preparation. 
eDelivery Newsletter No. 12 (May-June 2025)

 

 

15%

The content has been identified and is currently in progress to be prepared.

*All milestones presented in the table above are subject to confirmation or re-evaluation once the new MoU between DIGIT and DG CNECT is signed.

Technical Progress

Specifications: eDelivery AS4, SMP, BDXL, ebCore Party Id Profiles

Software product: Domibus

Software product: DomiSMP

Software product: DomiSML

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

Software product: Docker images

Service: PKI Service

Service: SML Service

Section 2: Evolutive Maintenance

Change Requests

KeySummaryTCreatedUpdatedStatusResolution
EDELGOV-134Case Sensitivity of partyIdType and partyId in Domibus pModeRequest for ChangeMar 26, 2025 15:48May 20, 2025 15:57

 

Unresolved
EDELGOV-133Support official Docker imagesRequest for ChangeMar 26, 2025 15:21May 20, 2025 17:12

 

Unresolved
EDELGOV-89Fulfill the requirements on the BDEW AS4 ProfileRequest for ChangeOct 28, 2022 17:03Feb 11, 2025 17:33

 

Unresolved
EDELGOV-76Request for investigation of using multihop functionality with AS4Request for ChangeNov 12, 2020 17:51Sept 28, 2022 07:56

 

On hold
EDELGOV-51Dynamic Service discovery - SML/SMP change requestRequest for ChangeSept 28, 2018 15:04Feb 11, 2025 16:35

 

Unresolved

Release Calendar