Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.8

 

100%

Status
colourGreen
titlecompleted


Domibus 5.1.3

 

 

100%

Status
colourGreen
titlecompleted


Domibus 5.1.4

 

 

20%

Status
colourYellow
titlein progress


Domibus 5.2 RC

Q4 2024

67%

Status
colourYellow
titlein progress

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q4 2024

Q4 2024

0%

Status
colourGrey
titlenot started

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q1 2025

Q1 2025

0%

Status
colourGrey
titlenot started


Domibus 6.0 RC

Q2 2025

Q3 2025

0%

Status
colourGrey
titlenot started

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

Q4 2025

Q4 2025

0%

Status
colourGrey
titlenot started


DomiSML 5.0 RC

0%

Status
colourGrey
titlenot started


DomiSML 5.0 FR

0%

Status
colourGrey
titlenot started

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.1 RC

60%

Status
colourYellow
titlein progress


DomiSMP 5.1 FR

0%

Status
colourGrey
titlenot started


eDelivery AS4, SMP, BDXL & ebCore Party Id 2.0 profiles

95%

Status
colourYellow
titlein progress

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

A first public consultation was held between July 2023 - November 2023.

A second public consultation was held between 8 March 2024 - 8 April 2024.

The specifications are to be tentatively adopted in July, after live testing during two events planned in June.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

52%

Status
colourYellow
titlein progress


Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile

52%

Status
colourBlue
titleON HOLD


Migration to GITLab

Q4 202412%

Status
colourBlue
titleON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations

 

100%

Status
colourGreen
titleCompleted

New documentation framework setup and support process implemented. New documentation site created.

  • Go live with the new documentation model pending adjustments in the Domibus release page.
  • Due to the postponing of the Domibus 5.2 release, release for which the premiere of the new documentation format was planned for, it was decided that the new format will be implemented with Domibus 5.0.8 release, once the new Domibus release page structure is validated.


Newsroom account for eDelivery (for mailing list management)

?

10%

Status
titleCANCELLED

The development of a newsroom account for eDelivery has been suspended.
Update eDelivery projects & stakeholders repository

50%

Status
colourYellow
titlein progress

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
eDelivery FAQ (overhaul of communication materials)

 

 

15%

Status
colourYellow
titlein progress

Updating eDelivery knowledge base and display of FAQ in various contexts.
eDelivery Self-Assessment and Cost-Analysis tools (overhaul of communication materials)

 

 

10%

Status
colourYellow
titlein progress

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Tutorial materials (overhaul of communication materials)

Tbc.

 

0%

Status
colourGrey
titlenot started


Conformant solutions presentation 

 

70%

Status
colourYellow
titlein progress

Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. 
Pitch and launch joint Building Blocks social media account

80%

Status
colourYellow
titlein progress

Launch social media accounts together with other Building Blocks.
eDelivery Interoperability Forum 29 February

 

100%

Status
colourGreen
titlecomplete

 
How-to video on DomiSMP 5.0 new features published

 

100%

Status
colourGreen
titlecomplete

 
eDelivery Interoperability Forum 18 April

25%

Status
colourYellow
titlein progress

 
eDelivery Informal Cooperation Network meeting 15 May

10%

Status
colourYellow
titlein progress

 
Interoperability Event 11 & 25 June

15%

Status
colourYellow
titlein progress

 
Webinar on eDelivery value proposition (Member States) 26 September

0%

Status
colourGrey
titlenot started

 
How-to video on Domibus new features 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Interoperability Forum 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

Status
colourGrey
titlenot started

 
Dynamic Discovery Webinar 12 December

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 7 (March 2024)

100%

Status
colourGreen
titlecompleteD

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Informal Cooperation Network meeting 15 May

 

 

5%

Status
colourYellow
titlein progress

 
Interoperability Event 11 June

 

 

0%

Status
colourGrey
titlenot started

 
Webinar on eDelivery value proposition (Member States)  26 September

 

 

0%

Status
colourGrey
titlenot started

 
How-to video on Domibus new features 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Interoperability Forum 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

Status
colourGrey
titlenot started

 
Dynamic Discovery Webinar 12 December

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 7 (March 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

Status
colourGrey
titlenot started

 

Overall Project Progress

Technical

...