Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 4.2.12

 

 

100%

Status
colourGreen
titlecompleted


Domibus 5.0.2

 

 

100%

Status
colourGreen
titlecompleted

(bug fix release - Fix migration scripts ongoing messages | Possibility to have a separate log containing all errors | 3rd Party libraries upgrade)
Domibus 5.0.3

 

 

100%

Status
colourGreen
titlecompleted


Domibus 5.1 RC

 

 

93%

Status
colourYellow
titlein progress

Postponed from the 13th January
Domibus 5.1 FR

 

 

-

Status
colourGrey
titlenot started


SML 4.2 FR

 

 

100%

Status
colourGreen
titlecompleted


DomiSML 4.3 RC

 

 

0%

Status
colourGrey
titlenot started


DomiSML 4.3 FR

 

 

0%

Status
colourGrey
titlenot started


DomiSMP 5.0 RC

 

 

68%

Status
colourYellow
titlein progress


DomiSMP 5.0 FR

 

 

0%

Status
colourGrey
titlenot started


eDelivery AS4 2.0 profile

 

 

75%

Status
colourYellow
titlein progress

main focus of this profile version is the upgrade to new cryptographic algorithms 
Upgrade conformance testing service

 

 

66%

Status
colourYellow
titlein progress


Migration to GITLab

 

Q4 202410%

Status
colourYellow
titlein progress

The preliminary exercise of duplicating the SMP and Domibus project in GITlab for viability test purposes concluded.
Migration to a new PKI service provider (CommisSign)

 

Q1 202390%

Status
colourYellow
titlein progress


Define and Implement new documentation model for the eDelivery sample implementations

 

 

15%

Status
colourYellow
titlein progress


eDelivery TO team transition to DIGIT TM2

 

 

100%

Status
colourGreen
titlecompleted


ITSRM2 - SML service security plan

 

 

100%

Status
colourGreen
titlecompleted


Newsroom account for eDelivery (for mailing list management)

 

 

2%

Status
colourYellow
titlein progress


Update eDelivery projects & stakeholders repository

 

 

2%

Status
colourYellow
titlein progress

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
Overhaul of eDelivery communication materials

 

15%

Status
colourYellow
titlein progress

This includes the eDelivery tutorial, flyers, leaflet, PPT presentation materials.
Increase average online engagement rate to 15 %  

 

 

50%

Status
colourYellow
titlein progress

The current average engagement rate on Twitter is 7-8%.

Increase the number of newsletter subscribers to 1300

 

 

30%

Status
colourYellow
titlein progress


Preparation of content for the DBB Newsletter No.3

 

 

100%

Status
colourGreen
titlecompleted


Preparation of content for the eDelivery Newsletter No.3

 

 

95%

Status
colourYellow
titlein progress


OOTS hands-on webinar. 26 January 2023

 

 

95%

Status
colourYellow
titlein progress


Webinar on exchanging large files with eDelivery. 7 March 2023

 

 

10%

Status
colourYellow
titlein progress


First meeting of the Informal Cooperation Network for eDelivery (ICN) 

 

(tentatively)

10%

Status
colourYellow
titlein progress


eDelivery Interoperability Forum. 3 May 2023

 

 

10%

Status
colourYellow
titlein progress


Webinar on dynamic discovery. 8 June 2023

 

 

10%

Status
colourYellow
titlein progress


Webinar on eDelivery: intro, value and success stories. 28 September 2023

 

 

10%

Status
colourYellow
titlein progress


Second meeting of the Informal Cooperation Network for eDelivery (ICN) 

 

 

0% 

Status
colourGrey
titlenot started


Overall Project Progress 

...